Roxane UK, Armathwaite Solar Array & Battery Storage (5 MW)

Roxane UK, Armathwaite Solar Array & Battery Storage is a 5 MW solar farm project in Westmorland and Furness, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 March 2026, not yet built; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtstatus in REPD
19 May 2026record last updated
Westmorland and Furnesscouncil area

Planning timeline

DateStage
19 August 2025Application submitted
17 March 2026Planning permission granted
17 March 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
19 May 2026
Operator or applicant
Roxane UK Limited
Planning authority
Westmorland and Furness
Planning application reference
2025/1585/FPA
Site area
10.7 ha
Address (REPD)
North of Roxane UK Ltd Armathwaite
Council area (by location)
Westmorland and Furness
Time to decision
30 weeks
Name in REPD
Roxane UK, Armathwaite - Solar Array & Battery Storage
REPD reference
16773

Who decides

ApplicationsWestmorland and FurnessUK
Decided applications (solar, wind, battery)6810,236
Refused30 (44%)19%
Solar refused14 of 4212%
Onshore wind refused14 of 1945%
Battery storage refused2 of 716%
Median time from submission to decision34.6 weeks17.0 weeks
Appeals lodged / allowed9 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Calthwaitebattery storage6permission expired5.5
Hay Close Wind Farmwind farm10appeal withdrawn5.8
Solar Panels at Devonshire Squaresolar farm30refused7.3
Bowscarsolar farm5permission expired7.4
Land at Skelton Radio Transmitter Sitesolar farm5application withdrawn8.4
Town End Farmsolar farm5permission expired9.2
Land at Wreaysolar farm5operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.7694, -2.7723).