Energy Projects Near You

Atcost Road (100 MW battery storage)

Atcost Road is a 100 MW battery storage project in Barking and Dagenham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 2 May 2024, no decision recorded; the record was last updated on 30 May 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
application submittedmay be out of datestatus in REPD
30 May 2024record last updated
Barking and Dagenhamcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
2 May 2024Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
application submitted
Record last updated
30 May 2024
Operator or applicant
O&G Group Limited
Planning authority
Barking and Dagenham
Planning application reference
24/00625/FULL
Address (REPD)
11 Atcost Road, Barking
Council area (by location)
Barking and Dagenham
Name in REPD
Atcost Road - Battery Storage Facility
REPD reference
16419

Who decides

ApplicationsBarking and DagenhamUK
Decided applications (solar, wind, battery)1310,236
Refused0 (0%)19%
Solar refused0 of 1112%
Onshore wind refused0 of 245%
Median time from submission to decision7.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ford Wind Park - Dagenhamwind farm5.9operational3.2
Riverside Energy Parkbattery storage20approved, not built3.6
Solar Panels at Hedgehog Grove Solar Farmsolar farm98application submitted8.6
Manor Farm, Dartford Roadbattery storage212application submitted9.2
Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storagesolar farm16approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5169, 0.1045).