Energy Projects Near You

Solar, wind and battery projects near London (SE28)

79 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SE28 (Greenwich): 10 are waiting for a planning decision, 51 approved but not yet running, 8 operational. The largest live scheme is Manor Farm, Dartford Road (212 MW battery storage, application submitted on 5 June 2025, no decision recorded), 7.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

79projects within 10 km
10awaiting a decision
51approved, not running
8operational

Projects within 10 km of SE28

Projects of 1 MW and more (20)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Atcost Roadbattery storagebattery storage100application submitted may be out of dateupdated May 2024May 2024—May 2024Barking and Dagenham1.7
Crossness Sewage Works PVrooftop solarrooftop solar1.5operationalupdated Jan 2012——Jan 2012Bexley2.5
Crossness Sewage Works Turbinewind turbinewind turbine2.5operationalupdated Jan 2015Nov 2010granted Dec 2010Jan 2015Bexley2.7
Beckton Sewage Treatment Workswind farmwind farm2.2operationalupdated Feb 2015——Feb 2015Newham3.1
Riverside Energy Parkbattery storagebattery storage20approved, not built may be out of dateupdated Apr 2022Nov 2018granted Apr 2020Apr 2022Bexley3.5
Riverside Energy Park (REP)rooftop solarrooftop solar1approved, not built may be out of dateupdated Sep 2020Nov 2018granted Apr 2020Sep 2020Bexley3.5
Riverside Resource Recovery Facility Battery Storagebattery storagebattery storage2.5under constructionupdated Jan 2021Dec 2020—Jan 2021Bexley3.6
Ford Wind Park - Dagenhamwind farmwind farm5.9operationalupdated Aug 2011Mar 2003granted Jul 2003Aug 2011Barking and Dagenham3.8
Ford Motor Company Ltd (Extension)wind turbinewind turbine2operationalupdated Sep 2011Apr 2009granted Jul 2009Sep 2011Barking and Dagenham4.4
Queen Elizabeth Hospital, Stadium Roadrooftop solarrooftop solar1.6refusedupdated Dec 2025Oct 2025refused Nov 2025Dec 2025Greenwich4.5
Thameside DCrooftop solarrooftop solar1operationalupdated Feb 2016——Feb 2016Greenwich5.4
The O2 Arenawind farmwind farm3approved, not built may be out of dateupdated Oct 2021Jun 2021granted Sep 2021Oct 2021Greenwich6.8
Alcatel, Telegraph Houserooftop solarrooftop solar1.3refusedupdated Dec 2025Sep 2025refused Oct 2025Dec 2025Greenwich6.8
Manor Farm, Dartford Roadbattery storagebattery storage212application submittedupdated Jul 2025Jun 2025—Jul 2025Bexley7.8
Bywaters’ Materials Recovery Facility Solar Arrayrooftop solarrooftop solar1operationalupdated Feb 2017Oct 2015granted Dec 2015Feb 2017Tower Hamlets8.0
Solar Panels at Hedgehog Grove Solar Farmsolar farmsolar farm98application submittedupdated Apr 2026Mar 2026—Apr 2026Tower Hamlets8.4
Ocado Operating Limited, New Purfleet Roadrooftop solarrooftop solar2.8approved, not builtupdated May 2025Mar 2025granted May 2025May 2025Thurrock9.0
Olympic Park Wind Turbinewind turbinewind turbine2.5abandonedupdated Oct 2010Jan 2007granted Sep 2007Oct 2010Newham9.2
North Cray Roadbattery storagebattery storage200refusedupdated Jan 2026Apr 2025refused Oct 2025Jan 2026Bexley9.3
Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storagesolar farmsolar farm16approved, not builtupdated Feb 2025Feb 2024granted Jul 2024Feb 2025Thurrock9.3
Smaller schemes under 1 MW, mostly rooftop solar (59)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Twin Tumps Wayrooftop solarrooftop solar0.6operationalupdated Mar 2022Feb 2022granted Dec 2022Mar 2022Greenwich0.5
Atlantis Avenue, Beckton Solar PV Systemsrooftop solarrooftop solar0.4approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Newham2.0
The I O Centre, Skeffington Streetrooftop solarrooftop solar0.2refusedupdated Feb 2026Nov 2025refused Jan 2026Feb 2026Greenwich2.3
Nic Ice, Thames Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025Barking and Dagenham2.5
University Of East London Dockland Campus, University Way - Soalr Panelsrooftop solarrooftop solar—approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Newham2.7
Thames Innovation Centre, Veridion Wayrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025May 2025granted Jul 2025Sep 2025Bexley2.8
London Design and Engineering UTC, University Waywind farmwind farm0.2application submittedMay 2026——Newham2.9
Knowledge Dock, University Wayrooftop solarrooftop solar0.1approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Newham2.9
Manor Joinery Estate, Eastern Approach Alfreds Wayrooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Dec 2022granted Feb 2023Mar 2023Barking and Dagenham3.3
Brookhill Estate Regenerationrooftop solarrooftop solar0.1approved, not built may be out of dateupdated May 2022Apr 2022granted Mar 2023May 2022Greenwich3.3
Circular 13, Unit B, Gascoigne Roadrooftop solarrooftop solar1approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Barking and Dagenham3.3
Sainsbury, Claps Gate Lanerooftop solarrooftop solar0.4application submittedMay 2026——Newham3.4
Dagenham Motors, Ripple Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2023May 2023granted Jun 2023Jun 2023Barking and Dagenham3.5
New England Industrial Estate Developmentrooftop solarrooftop solar0.2under constructionupdated May 2023Mar 2021granted Sep 2021May 2023Barking and Dagenham3.5
Thames Gateway Park, Choats Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2023May 2023granted Jun 2023Jun 2023Barking and Dagenham3.6
Pooles Lanerooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Jul 2025granted Aug 2025Nov 2025Barking and Dagenham3.8
Goresbrook School, Cook Roadrooftop solarrooftop solar0.4approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Barking and Dagenham3.9
Newham Dockside - Photovoltaic Panelsrooftop solarrooftop solar0.4approved, not builtupdated Mar 2022Jan 2022granted Mar 2022Mar 2022Newham3.9
JJ Food Service, Orion Park Messina Wayrooftop solarrooftop solar0.6approved, not builtupdated Oct 2023Oct 2023granted Nov 2023Oct 2023Barking and Dagenham4.2
Ellen Wilkinson School, Tollgate Road Solar PhotovoltaicPanelsrooftop solarrooftop solar0.2approved, not builtupdated May 2024Jan 2024granted Apr 2024May 2024Newham4.3
Siemens Roadrooftop solarrooftop solar0.7refusedupdated Jun 2023Apr 2023refused Jun 2023Jun 2023Greenwich4.3
Siemens Road, Westminster Industrial Estaterooftop solarrooftop solar0.7approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Greenwich4.3
Siemens Road, Westminster Industrial Estaterooftop solarrooftop solar0.7approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Greenwich4.3
Swan Road, Westminster Industrial Estaterooftop solarrooftop solar0.7refusedupdated Jun 2023Apr 2023refused Jun 2023Jun 2023Greenwich4.4
Roman Road Primary School, Roman Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Newham4.5
Leyes Road - New SEN Schoolrooftop solarrooftop solar0.2under constructionupdated Sep 2025Sep 2023granted Nov 2023Sep 2025Newham4.6
The Valley, Floyd Roadrooftop solarrooftop solar0.7approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Greenwich4.9
Stone Lake Retail Park, Woolwich Roadrooftop solarrooftop solar0.1approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Greenwich5.0
Ceme Campus, Marsh Wayrooftop solarrooftop solar0.9approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023Havering5.1
Newham Leisure Centre, Prince Regent Lanerooftop solarrooftop solar0.2application submitted may be out of dateupdated Feb 2023Dec 2022—Feb 2023Newham5.3
Newham University Hospital, Glen Roadrooftop solarrooftop solar0.8approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026Newham5.3
Custom Housebattery storagebattery storage0.2approved, not builtupdated Sep 2025Feb 2025granted Aug 2025Sep 2025Newham5.6
Plashet Schoolrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Newham5.6
The Mallrooftop solarrooftop solar—approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Bexley5.9
Bexleyheath Superbowl, Albion Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Bexley6.0
James Watt Wayrooftop solarrooftop solar0.6approved, not builtupdated Nov 2021Nov 2021granted Jan 2022Nov 2021Bexley6.1
Hunters Hall Primary School, Alibon Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Barking and Dagenham6.2
Millennium Retail Park - Flats & Retail Spacerooftop solarrooftop solar0.3application submitted may be out of dateupdated Sep 2024May 2024—Sep 2024Greenwich6.3
Avery Hill Campus, Avery Hill Roadrooftop solarrooftop solar0.5approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Greenwich6.4
The Exchange Mall, High Roadrooftop solarrooftop solar0.7approved, not builtupdated Dec 2024Oct 2024granted Nov 2024Dec 2024Redbridge6.8
David Lloyd Leisure Limited, Corner Of Weigall Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Greenwich7.2
Paul Rhodes Bakery Limited, Lassell Streetrooftop solarrooftop solar—refusedupdated May 2025Mar 2025refused May 2025May 2025Greenwich7.3
Segro Park Canning, Town Bidder Street, Unit 2rooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Newham7.3
University Of East London - 650 Student accommodation & Teaching and learningrooftop solarrooftop solar0.2under constructionupdated Jun 2026Apr 2023granted Aug 2025Jun 2026Newham8.0
University Of East London, Stratford Cam PV Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Newham8.0
Barking And Dagenham College, Dagenham Roadrooftop solarrooftop solar0.8approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025Barking and Dagenham8.1
Barking & Dagenham College Of Technology, Dagenham Road Solarrooftop solarrooftop solar—no application requiredupdated May 2025Apr 2025—May 2025Barking and Dagenham8.1
Citibank, 25 Canada Square - Office Fit-Out & Refurbishmentrooftop solarrooftop solar—no application requiredupdated Feb 2022——Feb 2022Tower Hamlets8.4
William Torbitt School, Eastern Avenuerooftop solarrooftop solar0.2application submittedMay 2026——Redbridge8.5
King George Hospital, Barley Lanerooftop solarrooftop solar0.8application submittedupdated Feb 2026Jan 2026—Feb 2026Redbridge8.8
Redbridge Institute Of Adult Education, Gaysham Avenuerooftop solarrooftop solar0.1approved, not builtupdated Nov 2025Sep 2025granted Oct 2025Nov 2025Redbridge8.9
Westfield Stratford City, Montfichet Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Newham9.0
David Lloyd Leisure, Baugh Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2026Jul 2025granted Sep 2025Jan 2026Bexley9.1
Maidstone Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Bexley9.3
Aveley Landfill, Sandy Lane PV Solar Array & Battery Energy Storagebattery storagebattery storage—approved, not builtupdated Feb 2025Feb 2024granted Jul 2024Feb 2025Thurrock9.3
Dartford Grammar School For Boys, West Hillrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Dartford9.4
Northern Gateway Distribution Centre, Central Road Northrooftop solarrooftop solar0.8approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Dartford9.6
Northern Gateway Distribution Centre,Central Road Northrooftop solarrooftop solar0.6application submittedJun 2026——Dartford9.7
One Hundred House, Brunel Wayrooftop solarrooftop solar0.8approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Dartford9.8

Distance from the average position of the SE28 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm21100114
Rooftop solar636454622.1
Wind farm411203.2
Wind turbine300200
Battery storage72401335

MW in pipeline: pending, approved and under-construction capacity.

How Greenwich decides solar, wind and battery applications

ApplicationsGreenwichUK
Decided applications (solar, wind, battery)1510,236
Refused6 (40%)19%
Solar refused6 of 1412%
Onshore wind refused0 of 145%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Greenwich

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SE28, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.