Energy Projects Near You

Callagheen (22.8 MW wind farm)

Callagheen is a 22.8 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2005; the record was last updated on 8 October 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22.8 MWwind farm
operationalstatus in REPD
8 October 2013record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
27 December 2001Application submitted
8 April 2004Planning permission granted
16 May 2005Construction started
1 December 2005Operational

Project details

Technology
wind farm
Capacity
22.8 MW
Status (REPD)
operational
Record last updated
8 October 2013
Operator or applicant
B9 / Renewable Energy Systems (RES)
Planning authority
Fermanagh and Omagh
Planning application reference
L2001/1514
Turbines
13
Address (REPD)
Garrison, near borders
Council area (by location)
Fermanagh and Omagh
Time to decision
119 weeks
REPD reference
4673

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Callagheen Extwind farm13.8application withdrawn4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.4178, -8.093).