Derrynaveigh Wind Farm (5.6 MW)
Derrynaveigh Wind Farm is a 5.6 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 September 2015; the record was last updated on 27 September 2015.
5.6 MWwind farm
refusedstatus in REPD
27 September 2015record last updated
Fermanagh and Omaghcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 20 November 2013 | Application submitted |
| 24 September 2015 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 5.6 MW
- Status (REPD)
- refused
- Record last updated
- 27 September 2015
- Operator or applicant
- Derrynaveigh Wind Farm Ltd
- Planning authority
- Fermanagh and Omagh
- Planning application reference
- L/2013/0623/F
- Turbines
- 7
- Address (REPD)
- Land approximately 400m north of Drumbulcan Road, Irvinestown, Co. Fermanagh, Northern Ireland
- Council area (by location)
- Fermanagh and Omagh
- Time to decision
- 96 weeks
- REPD reference
- 4283
Who decides
| Applications | Fermanagh and Omagh | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 74 | 10,236 |
| Refused | 12 (16%) | 19% |
| Solar refused | 0 of 1 | 12% |
| Onshore wind refused | 12 of 70 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 87.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 8 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Carricknabrattoge | wind farm | 12.1 | application withdrawn | 4.6 |
| Garrane | wind farm | 17.5 | application withdrawn | 6.0 |
| Tappaghan Extension | wind farm | 9 | operational | 6.8 |
| Tappaghan | wind farm | 19.5 | operational | 6.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.4968, -7.6347).