Derrynaveigh Wind Farm (5.6 MW)

Derrynaveigh Wind Farm is a 5.6 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 September 2015; the record was last updated on 27 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.6 MWwind farm
refusedstatus in REPD
27 September 2015record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
20 November 2013Application submitted
24 September 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
5.6 MW
Status (REPD)
refused
Record last updated
27 September 2015
Operator or applicant
Derrynaveigh Wind Farm Ltd
Planning authority
Fermanagh and Omagh
Planning application reference
L/2013/0623/F
Turbines
7
Address (REPD)
Land approximately 400m north of Drumbulcan Road, Irvinestown, Co. Fermanagh, Northern Ireland
Council area (by location)
Fermanagh and Omagh
Time to decision
96 weeks
REPD reference
4283

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carricknabrattogewind farm12.1application withdrawn4.6
Garranewind farm17.5application withdrawn6.0
Tappaghan Extensionwind farm9operational6.8
Tappaghanwind farm19.5operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.4968, -7.6347).