Energy Projects Near You

Drum Hollistan Wind Farm (35 MW)

Drum Hollistan Wind Farm is a 35 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 23 September 2020; the record was last updated on 25 June 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWwind farm
refusedstatus in REPD
25 June 2020record last updated
Highlandcouncil area

Planning timeline

DateStage
17 February 2020Application submitted
23 September 2020Refused by the planning authority

Project details

Technology
wind farm
Capacity
35 MW
Status (REPD)
refused
Record last updated
25 June 2020
Operator or applicant
Muirden Energy
Planning authority
Highland
Planning application reference
20/00645/FUL
Turbines
7
Turbine height
125 m
Address (REPD)
the Sandside Estate, Land 2215M SW Of Under Keepers, Sandside, Reay, Thurso
Council area (by location)
Highland
Time to decision
31 weeks
REPD reference
7686

Earlier applications for this site

ApplicationMWSubmittedOutcome
Drum Hollistan Wind Farm ECU000002435120 October 2016replaced by a revised application
Drum Hollistan Wind Farm 20/00645/FUL3517 February 2020refused on 23 September 2020

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Limekiln, Borlum Housebattery storage70application submitted4.3
Melvich Wind Energy Hubwind farm57.6application submitted4.7
Dounreay, Thursobattery storage34under construction5.5
Titan Battery Storagebattery storage500application submitted5.6
Limekiln Wind Farmwind farm79.8operational6.0
Dounreay Windfarmwind farm17.5refused on appeal6.2
Limekiln Wind Farm (Extension)wind farm21operational7.6
Limekiln Wind Farm (Extension) Batterybattery storage5operational7.6
South Shebsterwind farm10refused8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.5485, -3.8389).