Green Man Road, Navenby (400 MW battery storage)

Green Man Road, Navenby is a 400 MW battery storage project in North Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 9 May 2025, no decision recorded; the record was last updated on 13 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
application submittedstatus in REPD
13 June 2025record last updated
North Kestevencouncil area

Planning timeline

DateStage
9 May 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
application submitted
Record last updated
13 June 2025
Operator or applicant
Windel Energy / Canadian Solar
Planning authority
North Kesteven
Planning application reference
25/0491/FUL
Address (REPD)
N/O Green Man Road, Navenby, Lincoln
Council area (by location)
North Kesteven
Name in REPD
Green Man Road, Navenby - Battery Storage
REPD reference
13977

Who decides

ApplicationsNorth KestevenUK
Decided applications (solar, wind, battery)3510,236
Refused3 (9%)19%
Solar refused2 of 2912%
Onshore wind refused0 of 145%
Battery storage refused1 of 516%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hill Rise, Colebybattery storage1,000application submitted2.8
Branston solar parksolar farm18.9operational8.5
Branston Solar Park (extension)solar farm40under construction8.9
Fosse Green Energysolar farm350application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1106, -0.5214).