Energy Projects Near You

Hill Rise, Coleby (1,000 MW battery storage)

Hill Rise, Coleby is a 1,000 MW battery storage project in North Kesteven, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 15 May 2025, no decision recorded; the record was last updated on 2 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1,000 MWbattery storage
application submittedstatus in REPD
2 June 2025record last updated
North Kestevencouncil area

Planning timeline

DateStage
15 May 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
1,000 MW
Status (REPD)
application submitted
Record last updated
2 June 2025
Operator or applicant
Navenby Energy Limited
Planning authority
North Kesteven
Planning application reference
25/0533/FUL
Address (REPD)
The S/O Hill Rise, W/O Coleby & N/O Navenby, Lincoln
Council area (by location)
North Kesteven
Name in REPD
Hill Rise, Coleby - Battery Energy Storage
REPD reference
18790

Who decides

ApplicationsNorth KestevenUK
Decided applications (solar, wind, battery)3510,236
Refused3 (9%)19%
Solar refused2 of 2912%
Onshore wind refused0 of 145%
Battery storage refused1 of 516%
Median time from submission to decision10.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Green Man Road, Navenbybattery storage400application submitted2.8
Fosse Green Energysolar farm350application submitted7.2
Branston solar parksolar farm18.9operational7.3
Branston Solar Park (extension)solar farm40under construction7.8
Whisby Quarry, Eagle Roadfloating solar18approved, not built10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.1315, -0.5448).