Invershin Community Hall Wind Farm & Battery Storage (222 MW)

Invershin Community Hall Wind Farm & Battery Storage is a 222 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 February 2025, not yet built; the record was last updated on 15 April 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

222 MWwind farm
approved, not builtstatus in REPD
15 April 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
15 April 2021Application submitted
13 February 2025Section 36 consent granted (Scottish Ministers)

Project details

Technology
wind farm
Capacity
222 MW
Status (REPD)
approved, not built
Record last updated
15 April 2025
Operator or applicant
Garvary Wind Farm Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00003251
Turbines
37
Turbine height
180 m
Address (REPD)
4600m, Ne/O Invershin Community Hall, Invershin, Lairg
Council area (by location)
Highland
Time to decision
200 weeks
Name in REPD
Invershin Community Hall - Wind Farm & Battery Storage
REPD reference
8999

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Strath Tirry Wind Farmwind farm22.8approved, not built2.6
Shinness Wind Farmwind farm106application submitted3.1
Chleansaid Onshore Wind Farmwind farm96approved, not built5.7
Sallachy Estate Wind Farmwind farm43.2approved, not built5.7
Dalnessie Wind Farmwind farm67.5application withdrawn6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.1144, -4.4413).