Strath Tirry Wind Farm (22.8 MW)
Strath Tirry Wind Farm is a 22.8 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 June 2022, not yet built; the record was last updated on 12 January 2021. REPD also records that the planning permission expired on 7 June 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.
REPD also records that the planning permission expired on 7 June 2025, so the project may not go ahead in this form.
Planning timeline
| Date | Stage |
|---|---|
| 18 December 2020 | Application submitted |
| 7 June 2022 | Planning permission granted |
| 7 June 2025 | Permission expired |
Project details
- Technology
- wind farm
- Capacity
- 22.8 MW
- Status (REPD)
- approved, not built
- Record last updated
- 12 January 2021
- Operator or applicant
- REG Windpower Limited
- Planning authority
- Highland
- Planning application reference
- 20/05067/FUL
- Turbines
- 4
- Turbine height
- 135 m
- Address (REPD)
- 1450m Ne/O Dalmichie
- Council area (by location)
- Highland
- Time to decision
- 77 weeks
- REPD reference
- 5172
Who decides
| Applications | Highland | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 160 | 10,236 |
| Refused | 68 (42%) | 19% |
| Solar refused | 0 of 15 | 12% |
| Onshore wind refused | 61 of 114 | 45% |
| Battery storage refused | 7 of 31 | 16% |
| Median time from submission to decision | 52.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 20 / 20 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Invershin Community Hall Wind Farm & Battery Storage | wind farm | 222 | approved, not built | 2.6 |
| Sallachy Estate Wind Farm | wind farm | 43.2 | approved, not built | 3.8 |
| Shinness Wind Farm | wind farm | 106 | application submitted | 4.4 |
| Chleansaid Onshore Wind Farm | wind farm | 96 | approved, not built | 4.8 |
| Dalnessie Wind Farm | wind farm | 67.5 | application withdrawn | 5.7 |
| Coille Linne Wind Farm | battery storage | 5 | application submitted | 8.2 |
| Coille Linne Wind Farm- Wind Turbines | wind farm | 108 | application submitted | 8.2 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0968, -4.4128).