Coille Linne Wind Farm (5 MW)

Coille Linne Wind Farm is a 5 MW battery storage project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 18 June 2025, no decision recorded; the record was last updated on 8 July 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWbattery storage
application submittedstatus in REPD
8 July 2025record last updated
Highlandcouncil area

Planning timeline

DateStage
18 June 2025Application submitted

Project details

Technology
battery storage (co-located with re)
Capacity
5 MW
Status (REPD)
application submitted
Record last updated
8 July 2025
Operator or applicant
Energiekontor (UK) Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005163
Address (REPD)
21.9km Nw/o Lairg, 16km Se/o Altnaharra, Lairg
Council area (by location)
Highland
Name in REPD
Coille Linne Wind Farm - Battery Energy Storage
REPD reference
16938

Recorded together with Coille Linne Wind Farm- Wind Turbines (108 MW wind farm, application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Lairg Wind Farmwind farm7.5operational3.8
Lairg 2 Wind Farmwind farm49.9under construction4.1
Sallachy Estate Wind Farmwind farm43.2approved, not built4.7
Braemorewind farm54permission expired6.2
Achany Wind Farmwind farm38operational6.4
Strath Tirry Wind Farmwind farm22.8approved, not built8.2
Rosehall Hill Forest Windfarmwind farm24.7operational9.3
Shinness Wind Farmwind farm106application submitted10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0238, -4.3992).