Energy Projects Near You

Lairg Wind Farm (7.5 MW)

Lairg Wind Farm is a 7.5 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 January 2012; the record was last updated on 19 April 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
19 April 2012record last updated
Highlandcouncil area

Planning timeline

DateStage
5 September 2006Application submitted
8 April 2008Planning permission granted
1 January 2012Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
19 April 2012
Operator or applicant
ABO Wind
Planning authority
Highland
Planning application reference
06/00376/FULSU
Turbines
3
Address (REPD)
Land To South Of Toroboll Lairg Highland
Council area (by location)
Highland
Time to decision
83 weeks
REPD reference
2796

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lairg 2 Wind Farmwind farm49.9under construction1.7
Coille Linne Wind Farm- Wind Turbineswind farm108application submitted3.8
Coille Linne Wind Farmbattery storage5application submitted3.8
Braemorewind farm54permission expired6.7
Sallachy Estate Wind Farmwind farm43.2approved, not built8.2
Achany Wind Farmwind farm38operational8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0027, -4.3487).