Energy Projects Near You

Achany Wind Farm (38 MW)

Achany Wind Farm is a 38 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 11 October 2010; the record was last updated on 8 August 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

38 MWwind farm
operationalstatus in REPD
8 August 2011record last updated
Highlandcouncil area

Planning timeline

DateStage
28 October 2005Application submitted
1 August 2006Refused by the planning authority
14 September 2007Planning permission granted
14 September 2007Appeal allowed
1 April 2009Construction started
11 October 2010Operational

Project details

Technology
wind farm
Capacity
38 MW
Status (REPD)
operational
Record last updated
8 August 2011
Operator or applicant
Scottish and Southern Energy (SSE)
Planning authority
Highland
Planning application reference
not recorded
Turbines
19
Address (REPD)
Albany Estate, Achany, Lairg, Highlands, IV27 4
Council area (by location)
Highland
Time to decision
98 weeks
REPD reference
3205

Who decides

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rosehall Hill Forest Windfarmwind farm24.7operational2.9
Braemorewind farm54permission expired4.4
Inveroykel Wind Farmwind farm191application submitted5.7
Achany Extension Wind Farmwind farm76approved, not built5.8
Coille Linne Wind Farm- Wind Turbineswind farm108application submitted6.4
Coille Linne Wind Farmbattery storage5application submitted6.4
Lairg 2 Wind Farmwind farm49.9under construction7.9
Sallachy Estate Wind Farmwind farm43.2approved, not built8.1
Strath Oykel Wind Farmwind farm72.6approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (58.0019, -4.5).