Strath Oykel Wind Farm (72.6 MW)
Strath Oykel Wind Farm is a 72.6 MW wind farm project in Highland, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 January 2025, not yet built; the record was last updated on 20 January 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.
Planning timeline
| Date | Stage |
|---|---|
| 16 May 2022 | Application submitted |
| 8 January 2025 | Section 36 consent granted (Scottish Ministers) |
| 8 January 2030 | Permission due to expire (unless work starts) |
Project details
- Technology
- wind farm
- Capacity
- 72.6 MW
- Status (REPD)
- approved, not built
- Record last updated
- 20 January 2025
- Operator or applicant
- Energiekontor (UK) Limited
- Planning authority
- Scottish Government (S36)
- Planning application reference
- ECU00003246
- Turbines
- 11
- Turbine height
- 200 m
- Address (REPD)
- Creagan Breaca, Strath Oykel, Isle of Skye
- Council area (by location)
- Highland
- Time to decision
- 138 weeks
- REPD reference
- 12290
The scheme also includes 5 MW of battery storage, recorded separately in REPD (approved, not built).
Who decides
As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Meall Buidhe Wind Farm | wind farm | 40 | approved, not built | 3.7 |
| Inveroykel Wind Farm | wind farm | 191 | application submitted | 4.3 |
| Rosehall Hill Forest Windfarm | wind farm | 24.7 | operational | 6.2 |
| Allt an Tuir Renewable Energy Park | wind farm | 59.4 | application submitted | 6.5 |
| Allt an Tuir Renewable Energy Park | battery storage | 12 | application submitted | 6.5 |
| Allt an Tuir Renewable Energy Park | solar farm | 18 | application submitted | 6.5 |
| Achany Extension Wind Farm | wind farm | 76 | approved, not built | 6.9 |
| Invercassley Windfarm | wind farm | 55 | refused on appeal | 7.1 |
| Achany Wind Farm | wind farm | 38 | operational | 8.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (57.9548, -4.619).