Kennoxhead Wind Farm (Phase 2) (28 MW)

Kennoxhead Wind Farm (Phase 2) is a 28 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 June 2022, not yet built; the record was last updated on 19 August 2022. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWwind farm
approved, not builtstatus in REPD
19 August 2022record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
31 January 2013Application submitted
14 June 2022Section 36 consent granted (Scottish Ministers)

Project details

Technology
wind farm
Capacity
28 MW
Status (REPD)
approved, not built
Record last updated
19 August 2022
Operator or applicant
Orsted Onshore Limited
Planning authority
Scottish Government (S36)
Planning application reference
EC00002101
Turbines
6
Turbine height
180 m
Address (REPD)
Kennoxhead, south of Hagshaw Hill
Council area (by location)
South Lanarkshire
Time to decision
489 weeks
REPD reference
11917

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Kennoxhead Wind Farmwind farm62under construction<0.1
Kennoxhead Wind Farm Extension (Phase 2)wind farm38.4approved, not built1.2
Kennoxhead Wind Farm Extension II (Penbreck) (Phase 2)wind farm45.6approved, not built3.8
Galawhistlewind farm66operational5.0
Spireslack Windfarmwind farm59.6application withdrawn6.1
Andershawwind farm36operational6.4
Hagshaw Hill Wind Farmwind farm7.8operational6.6
Hagshaw Hill Wind Farmwind farm7.8operational6.6
Hare Craig Windfarmwind farm36approved, not built7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4979, -3.9463).