Andershaw (36 MW wind farm)
Andershaw is a 36 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 2 November 2016; the record was last updated on 3 April 2018.
36 MWwind farm
operationalstatus in REPD
3 April 2018record last updated
South Lanarkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 9 July 2007 | Application submitted |
| 9 June 2014 | Planning permission granted |
| 28 October 2015 | Construction started |
| 2 November 2016 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 36 MW
- Status (REPD)
- operational
- Record last updated
- 3 April 2018
- Operator or applicant
- Statkraft UK
- Planning authority
- South Lanarkshire
- Planning application reference
- CL/07/0454
- Turbines
- 14
- Address (REPD)
- Andershaw Forest South of Douglas
- Council area (by location)
- South Lanarkshire
- Time to decision
- 361 weeks
- REPD reference
- 4110
Who decides
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Middle Muir Wind Farm | wind farm | 51 | operational | 2.7 |
| Bodinglee Wind Farm | wind farm | 266 | application submitted | 3.0 |
| Glentaggart Wind Farm | wind farm | 17 | appeal withdrawn | 3.4 |
| Glentaggart | battery storage | 42 | approved, not built | 4.6 |
| Red Moss | battery storage | 342 | approved, not built | 4.6 |
| M74 West Renewable Energy Park | battery storage | 50 | application submitted | 5.6 |
| Hagshaw Energy Cluster – Western Expansion | battery storage | 225 | application submitted | 5.6 |
| Hagshaw Energy Cluster – Western Expansion | solar farm | 60 | application submitted | 5.7 |
| Hagshaw Energy Cluster – Western Expansion | wind farm | 130 | application submitted | 5.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5093, -3.8463).