Energy Projects Near You

Middle Muir Wind Farm (51 MW)

Middle Muir Wind Farm is a 51 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 May 2019; the record was last updated on 16 May 2019. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

51 MWwind farm
operationalstatus in REPD
16 May 2019record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
7 February 2012Application submitted
26 September 2014Section 36 consent granted (Scottish Ministers)
16 January 2017Construction started
16 May 2019Operational

Project details

Technology
wind farm
Capacity
51 MW
Status (REPD)
operational
Record last updated
16 May 2019
Operator or applicant
Banks Renewables
Planning authority
Scottish Government (S36)
Planning application reference
CL/12/0056
Turbines
15
Address (REPD)
Middle Muir, Hamilton, Strathclyde (north of Crawfordjohn)
Council area (by location)
South Lanarkshire
Time to decision
137 weeks
Contracts for Difference
AR1
REPD reference
4440

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Glentaggart Wind Farmwind farm17appeal withdrawn1.8
Glentaggartbattery storage42approved, not built2.1
Red Mossbattery storage342approved, not built2.1
Bodinglee Wind Farmwind farm266application submitted2.7
Andershawwind farm36operational2.7
M74 West Renewable Energy Parkbattery storage50application submitted2.9
M74 West Renewable Energy Parksolar farm82.5application submitted4.7
M74 West Renewable Energy Parkwind farm165application submitted4.7
Limmer Hillwind farm99application withdrawn5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5129, -3.804).