Glentaggart Wind Farm (17 MW)
Glentaggart Wind Farm is a 17 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 30 March 2022.
17 MWwind farm
appeal withdrawnstatus in REPD
30 March 2022record last updated
South Lanarkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 26 October 2011 | Application submitted |
| 14 February 2020 | Application withdrawn |
| 14 February 2020 | Appeal withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 17 MW
- Status (REPD)
- appeal withdrawn
- Record last updated
- 30 March 2022
- Operator or applicant
- Ventient (formerly Infinis)
- Planning authority
- South Lanarkshire
- Planning application reference
- CL/11/0461
- Turbines
- 5
- Address (REPD)
- to the south east of the settlement of Glespin in South Lanarkshire
- Council area (by location)
- South Lanarkshire
- REPD reference
- 4594
Who decides
| Applications | South Lanarkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 89 | 10,236 |
| Refused | 30 (34%) | 19% |
| Solar refused | 2 of 20 | 12% |
| Onshore wind refused | 21 of 56 | 45% |
| Battery storage refused | 7 of 13 | 16% |
| Median time from submission to decision | 47.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 5 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Bodinglee Wind Farm | wind farm | 266 | application submitted | 1.4 |
| Middle Muir Wind Farm | wind farm | 51 | operational | 1.8 |
| M74 West Renewable Energy Park | solar farm | 82.5 | application submitted | 2.9 |
| M74 West Renewable Energy Park | wind farm | 165 | application submitted | 2.9 |
| M74 West Renewable Energy Park | battery storage | 50 | application submitted | 3.1 |
| Glentaggart | battery storage | 42 | approved, not built | 3.2 |
| Red Moss | battery storage | 342 | approved, not built | 3.2 |
| Andershaw | wind farm | 36 | operational | 3.4 |
| Limmer Hill | wind farm | 99 | application withdrawn | 3.7 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5287, -3.8049).