Bodinglee Wind Farm (266 MW)

Bodinglee Wind Farm is a 266 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 June 2023, no decision recorded; the record was last updated on 10 August 2023. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

266 MWwind farm
application submittedmay be out of datestatus in REPD
10 August 2023record last updated
South Lanarkshirecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
22 June 2023Application submitted

Project details

Technology
wind farm
Capacity
266 MW
Status (REPD)
application submitted
Record last updated
10 August 2023
Operator or applicant
Banks Group
Planning authority
Scottish Government (S36)
Planning application reference
ECU00004839
Turbines
37
Turbine height
250 m
Address (REPD)
Bodinglee Road, Wiston, Biggar
Council area (by location)
South Lanarkshire
REPD reference
13638

The scheme also includes 106 MW of battery storage, recorded separately in REPD (application submitted).

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Glentaggart Wind Farmwind farm17appeal withdrawn1.4
Middle Muir Wind Farmwind farm51operational2.7
M74 West Renewable Energy Parkwind farm165application submitted2.8
M74 West Renewable Energy Parksolar farm82.5application submitted2.8
Andershawwind farm36operational3.0
Hagshaw Energy Cluster – Western Expansionbattery storage225application submitted3.9
Hagshaw Energy Cluster – Western Expansionwind farm130application submitted3.9
Hagshaw Energy Cluster – Western Expansionsolar farm60application submitted3.9
Hagshaw Hill (Repowering)wind farm84operational4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5334, -3.8263).