M74 West Renewable Energy Park (50 MW)

M74 West Renewable Energy Park is a 50 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 24 September 2024, no decision recorded; the record was last updated on 13 December 2024. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
application submittedstatus in REPD
13 December 2024record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
24 September 2024Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
application submitted
Record last updated
13 December 2024
Operator or applicant
Renewco Power
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005019
Address (REPD)
M74 West Renewable Energy Park, Lanark, Strathclyde
Council area (by location)
South Lanarkshire
REPD reference
16027

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Red Mossbattery storage342approved, not built1.8
Glentaggartbattery storage42approved, not built1.8
Middle Muir Wind Farmwind farm51operational2.9
Glentaggart Wind Farmwind farm17appeal withdrawn3.1
Limmer Hillwind farm99application withdrawn3.5
Bodinglee Wind Farmwind farm266application submitted4.5
M74 West Renewable Energy Parksolar farm82.5application submitted4.9
M74 West Renewable Energy Parkwind farm165application submitted4.9
Andershawwind farm36operational5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5194, -3.7592).