Energy Projects Near You

Glentaggart (42 MW battery storage)

Glentaggart is a 42 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 January 2026, not yet built; the record was last updated on 25 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42 MWbattery storage
approved, not builtstatus in REPD
25 March 2026record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
16 July 2025Application submitted
29 January 2026Planning permission granted
28 January 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
42 MW
Status (REPD)
approved, not built
Record last updated
25 March 2026
Operator or applicant
South Lanarkshire Council / Brockwell Energy Limited
Planning authority
South Lanarkshire
Planning application reference
P/25/0685
Address (REPD)
Mid Rig, Glentaggart, Douglas, Biggar
Council area (by location)
South Lanarkshire
Time to decision
28 weeks
Name in REPD
Glentaggart - Battery Energy Storage
REPD reference
18360

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Red Mossbattery storage342approved, not built<0.1
M74 West Renewable Energy Parkbattery storage50application submitted1.8
Middle Muir Wind Farmwind farm51operational2.1
Glentaggart Wind Farmwind farm17appeal withdrawn3.2
Bodinglee Wind Farmwind farm266application submitted4.5
Andershawwind farm36operational4.6
Limmer Hillwind farm99application withdrawn5.1
Leadhills Wind Farmwind farm49refused5.4
M74 West Renewable Energy Parksolar farm82.5application submitted5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5056, -3.7736).