Leadhills Wind Farm (49 MW)

Leadhills Wind Farm is a 49 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 March 2015; the record was last updated on 7 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWwind farm
refusedstatus in REPD
7 April 2015record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
20 May 2013Application submitted
24 March 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
49 MW
Status (REPD)
refused
Record last updated
7 April 2015
Operator or applicant
Atmos
Planning authority
South Lanarkshire
Planning application reference
CL/13/0167
Turbines
14
Address (REPD)
Leadhills, Biggar, South Lanarkshire
Council area (by location)
South Lanarkshire
Time to decision
96 weeks
REPD reference
4392

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Harryburn Wind Farmwind farm67refused on appeal4.6
Glentaggartbattery storage42approved, not built5.4
Red Mossbattery storage342approved, not built5.4
Lowther Hills (North Lowther Energy Initiative)wind farm147refused on appeal5.7
Middle Muir Wind Farmwind farm51operational6.2
Andershawwind farm36operational6.8
M74 West Renewable Energy Parkbattery storage50application submitted7.1
Glentaggart Wind Farmwind farm17appeal withdrawn8.0
Leadhills Road, Elvanfoot Phase 2battery storage49.9application submitted8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4574, -3.7889).