Red Moss (342 MW battery storage)

Red Moss is a 342 MW battery storage project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 June 2025, not yet built; the record was last updated on 26 August 2025. As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

342 MWbattery storage
approved, not builtstatus in REPD
26 August 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
14 January 2025Application submitted
19 June 2025Section 36 consent granted (Scottish Ministers)

Project details

Technology
battery storage (stand-alone storage)
Capacity
342 MW
Status (REPD)
approved, not built
Record last updated
26 August 2025
Operator or applicant
Green Switch Capital Limited
Planning authority
Scottish Government (S36)
Planning application reference
ECU00005043
Address (REPD)
Red Moss, B7078, Crawfordjohn, Biggar
Council area (by location)
South Lanarkshire
Time to decision
22 weeks
Name in REPD
Red Moss - Battery Storage
REPD reference
15980

Who decides

As a project over 50 MW in Scotland, it is decided by Scottish Ministers under Section 36. Scottish Government (S36) refused 18% of 334 decided solar, wind and battery applications in REPD (median 127 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Glentaggartbattery storage42approved, not built<0.1
M74 West Renewable Energy Parkbattery storage50application submitted1.8
Middle Muir Wind Farmwind farm51operational2.1
Glentaggart Wind Farmwind farm17appeal withdrawn3.2
Bodinglee Wind Farmwind farm266application submitted4.5
Andershawwind farm36operational4.6
Limmer Hillwind farm99application withdrawn5.1
Leadhills Wind Farmwind farm49refused5.4
M74 West Renewable Energy Parksolar farm82.5application submitted5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5056, -3.7736).