Manor Farm - Pertenhall (15 MW solar farm)

Manor Farm - Pertenhall is a 15 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 October 2015; the record was last updated on 4 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
operationalstatus in REPD
4 January 2016record last updated
Bedfordcouncil area

Planning timeline

DateStage
20 May 2014Application submitted
19 November 2014Planning permission granted
1 September 2015Construction started
17 October 2015Operational

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
4 January 2016
Operator or applicant
Prosolia UK
Planning authority
Bedford
Planning application reference
14/00986/MAF
Address (REPD)
Land South Of Manor Farm Green End Pertenhall Bedfordshire
Council area (by location)
Bedford
Time to decision
26 weeks
REPD reference
2299

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cobholden Battery Storagebattery storage100approved, not built4.3
Staughton Airfield Solar Farmsolar farm40operational5.2
Bicton Industrial Park, Stow Road Solar Farmsolar farm8approved, not built5.4
Bicton Wind Farmwind farm9refused6.1
Rookery Farm Solar Farmsolar farm5.3operational6.2
Rookery Farm, Kimbolton Road Solar Farmsolar farm50approved, not built6.9
Rookery Farm, Kimbolton Roadbattery storage50approved, not built6.9
Chelveston Airfieldsolar farm16operational7.9
Chelveston Renewable Energy Park Solar Extensionsolar farm19.5operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2679, -0.4234).