Ora More (15 MW wind farm)

Ora More is a 15 MW wind farm project in Fermanagh and Omagh, Northern Ireland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2017; the record was last updated on 3 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
operationalstatus in REPD
3 May 2017record last updated
Fermanagh and Omaghcouncil area

Planning timeline

DateStage
15 December 2005Application submitted
30 March 2011Planning permission granted
15 November 2015Construction started
30 March 2017Operational

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
3 May 2017
Operator or applicant
Natural Power
Planning authority
Fermanagh and Omagh
Planning application reference
L/2005/3070/F
Turbines
6
Address (REPD)
Ora More Hill, in the Townlands of Killycreen East, Ora Beg and Mullylusty, near Boho and Belcoo, Co Fermanagh
Council area (by location)
Fermanagh and Omagh
Time to decision
276 weeks
REPD reference
4654

Who decides

ApplicationsFermanagh and OmaghUK
Decided applications (solar, wind, battery)7410,236
Refused12 (16%)19%
Solar refused0 of 112%
Onshore wind refused12 of 7045%
Battery storage refused0 of 316%
Median time from submission to decision87.9 weeks17.0 weeks
Appeals lodged / allowed8 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ora More Extensionwind farm6permission expired<0.1
Belmore Mountainwind farm30application withdrawn3.8
Tullinoidwind farm6application withdrawn9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.3385, -7.8959).