Energy Projects Near You

Priestgill Wind Farm (46.2 MW)

Priestgill Wind Farm is a 46.2 MW wind farm project in South Lanarkshire, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 September 2025; the record was last updated on 16 December 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

46.2 MWwind farm
under constructionstatus in REPD
16 December 2025record last updated
South Lanarkshirecouncil area

Planning timeline

DateStage
13 December 2016Application submitted
16 August 2017Refused by the planning authority
14 November 2017Appeal lodged
7 December 2018Appeal allowed
15 December 2021Planning permission granted
1 September 2025Construction started

Project details

Technology
wind farm
Capacity
46.2 MW
Status (REPD)
under construction
Record last updated
16 December 2025
Operator or applicant
Muirhall Energy
Planning authority
South Lanarkshire
Planning application reference
CL/17/0009
Appeal reference
PPA-380-2075
Turbines
7
Turbine height
200 m
Address (REPD)
Priestgill Wind Farm, Little Gill Farm, Abington, Biggar, Strathclyde
Council area (by location)
South Lanarkshire
Time to decision
261 weeks
Contracts for Difference
AR6
REPD reference
6363

Who decides

ApplicationsSouth LanarkshireUK
Decided applications (solar, wind, battery)8910,236
Refused30 (34%)19%
Solar refused2 of 2012%
Onshore wind refused21 of 5645%
Battery storage refused7 of 1316%
Median time from submission to decision47.4 weeks17.0 weeks
Appeals lodged / allowed6 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grayside Wind Farmwind farm147application submitted4.9
Clyde Wind Farm Extension (Clyde 2)wind farm173operational6.5
M74 West Renewable Energy Parkbattery storage50application submitted6.9
Red Mossbattery storage342approved, not built7.8
Glentaggartbattery storage42approved, not built7.8
Harryburn Wind Farmwind farm67refused on appeal7.8
Leadhills Road, Elvanfoot Phase 2battery storage49.9application submitted8.0
Elvanfoot, Leadhills Roadbattery storage9.8approved, not built8.1
Elvanfoot, Leadhills Road - Phase 3 - BESSbattery storage25application submitted8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.5112, -3.6507).