Spango Community Wind Farm (49 MW, REPD 4782)

Spango Community Wind Farm is a 49 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 24 September 2015; the record was last updated on 27 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWwind farm
refusedstatus in REPD
27 September 2015record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
10 November 2014Application submitted
24 September 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
49 MW
Status (REPD)
refused
Record last updated
27 September 2015
Operator or applicant
Community Wind Power
Planning authority
Dumfries and Galloway
Planning application reference
14/P/3/0560
Turbines
12
Turbine height
145 m
Address (REPD)
Spango (Mid Rig/Black Hill), northeast of Kirkconnel, Kirkconnel, Sanquhar
Council area (by location)
Dumfries and Galloway
Time to decision
45 weeks
REPD reference
4782

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Spango Community Wind Farmwind farm49application withdrawn1.2
Sandy Knowe Wind Farm Extensionwind farm21.6approved, not built4.0
Lagrae Battery Energy Storage Systembattery storage400application submitted4.9
Wind Turbines at Former Glenmuckloch Surface Coal Mine North Of Kirkconnelwind farm33.6application submitted5.7
Glenmuckloch Wind Farmwind farm33.6approved, not built5.8
Sandy Knowe Wind Farmwind farm81.6operational6.9
Whiteside Hillwind farm25.3operational7.0
Rowancraig North Wind Farmwind farm36application submitted7.2
Kennoxhead Wind Farm Extension II (Penbreck) (Phase 2)wind farm45.6approved, not built7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4076, -3.9616).