Spango Community Wind Farm (49 MW, REPD 4482)

Spango Community Wind Farm is a 49 MW wind farm project in Dumfries and Galloway, Scotland. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 30 June 2014; the record was last updated on 25 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49 MWwind farm
application withdrawnstatus in REPD
25 September 2014record last updated
Dumfries and Gallowaycouncil area

Planning timeline

DateStage
10 January 2014Application submitted
30 June 2014Application withdrawn

Project details

Technology
wind farm
Capacity
49 MW
Status (REPD)
application withdrawn
Record last updated
25 September 2014
Operator or applicant
Community Wind Power Limited
Planning authority
Dumfries and Galloway
Planning application reference
13/P/3/0578
Turbines
14
Address (REPD)
4km north of Sanquhar
Council area (by location)
Dumfries and Galloway
REPD reference
4482

Who decides

ApplicationsDumfries and GallowayUK
Decided applications (solar, wind, battery)10610,236
Refused40 (38%)19%
Solar refused1 of 1812%
Onshore wind refused33 of 7245%
Battery storage refused6 of 1616%
Median time from submission to decision60.9 weeks17.0 weeks
Appeals lodged / allowed19 / 17—

Other large projects within 10 km

ProjectTypeMWStatuskm
Spango Community Wind Farmwind farm49refused1.2
Sandy Knowe Wind Farm Extensionwind farm21.6approved, not built4.4
Lagrae Battery Energy Storage Systembattery storage400application submitted6.1
Lowther Hills (North Lowther Energy Initiative)wind farm147refused on appeal6.4
Glenmuckloch Wind Farmwind farm33.6approved, not built6.8
Wind Turbines at Former Glenmuckloch Surface Coal Mine North Of Kirkconnelwind farm33.6application submitted6.9
Kennoxhead Wind Farm Extension II (Penbreck) (Phase 2)wind farm45.6approved, not built7.2
Wind Turbines at Herds Hill Wind Farmwind farm10.3application submitted7.7
Rowancraig North Wind Farmwind farm36application submitted8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (55.4123, -3.9436).