Energy Projects Near You

Solar, wind and battery projects near Cleckheaton (BD19)

53 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BD19 (Kirklees): 3 are waiting for a planning decision, 45 approved but not yet running, 1 operational. The largest live scheme is Midland Road (80 MW battery storage, approved on 20 December 2024, not yet built), 8.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

53projects within 10 km
3awaiting a decision
45approved, not running
1operational

Projects within 10 km of BD19

Projects of 1 MW and more (14)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Roydsdale Way, Unit 6rooftop solarrooftop solar1.6approved, not builtupdated Apr 2026Jan 2026granted Mar 2026Apr 2026Bradford3.3
Swaledale House, Weaverthorpe Roadrooftop solarrooftop solar2approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Bradford4.2
Princes Soft Drinks Distributionwind turbinewind turbine2refusedupdated Apr 2011May 2008refused May 2009Apr 2011Bradford4.2
Mars Petcarewind turbinewind turbine2abandonedupdated Mar 2015Dec 2009granted Sep 2010Mar 2015Kirklees4.5
Former Howden Clough, Howden Clough Road Battery Unitsbattery storagebattery storage2approved, not builtupdated Jul 2023Oct 2022granted Apr 2023Jul 2023Leeds5.8
Howden Clough Landfill, Howden Clough Road Solar Farmsolar farmsolar farm2.4application submittedupdated Feb 2026Jan 2026—Feb 2026Leeds5.8
Aflex Hose, Dyson Wood Way - olar Panelsrooftop solarrooftop solar1.1approved, not builtupdated Jun 2024Apr 2024granted Jun 2024Jun 2024Kirklees6.5
Ashday Hall Farm, Ashday Lanebattery storagebattery storage65approved, not builtupdated Mar 2025Aug 2024granted Mar 2025Mar 2025Calderdale7.5
Lowfields Energy Storage Projectbattery storagebattery storage49.9approved, not built may be out of dateupdated Oct 2025Dec 2022granted Mar 2023Oct 2025Calderdale8.2
Midland Roadbattery storagebattery storage80approved, not builtupdated Sep 2025Oct 2023granted Dec 2024Sep 2025Bradford8.9
Stor Generation Plantbattery storagebattery storage12approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Bradford9.1
Dewsbury Sewage, Clough Lanesolar farmsolar farm1approved, not builtupdated Jun 2026Jul 2024granted May 2026Jun 2026Wakefield9.5
Haigh Hall Solar Farmsolar farmsolar farm5operationalupdated Jun 2017May 2016—Jun 2017Leeds9.5
Stainland Road, Salterhebblebattery storagebattery storage25approved, not built may be out of dateupdated Apr 2025Jun 2021granted Sep 2021Apr 2025Calderdale10.0
Smaller schemes under 1 MW, mostly rooftop solar (39)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wesco Aircraft Emea, Leeds Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024Kirklees4.0
Appleton Academy, Woodside Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Bradford4.1
Sedbergh Sports and Leisure Centrerooftop solarrooftop solar0.2under constructionupdated Apr 2026——Apr 2026Bradford4.8
St Matthews CE Primary School, Ivy House Roadrooftop solarrooftop solar0.2application submittedJun 2026——Bradford5.4
Bradford Forster Academyrooftop solarrooftop solar0.4approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Bradford6.0
Unit S, Gildersome Spur, Gildersomerooftop solarrooftop solar0.1approved, not builtupdated Oct 2022Aug 2022granted Oct 2022Oct 2022Leeds6.3
Gildersome Spurrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Oct 2022Aug 2022granted Oct 2022Oct 2022Leeds6.3
Gelderd Road, Gildersomerooftop solarrooftop solar0.2approved, not builtupdated Feb 2022Dec 2021granted Feb 2022Feb 2022Leeds6.4
Stone Pits Lane, Morleyrooftop solarrooftop solar—approved, not builtupdated Apr 2021Feb 2021granted Mar 2021Apr 2021Leeds6.4
Aflex House, Dyson Wood Wayrooftop solarrooftop solar0.9approved, not builtupdated Apr 2023Nov 2022granted Jan 2023Apr 2023Kirklees6.6
Station Road Energy Storage Facilitybattery storagebattery storage—approved, not built may be out of dateupdated May 2024Aug 2021granted Mar 2022May 2024Kirklees6.7
Huddersfield Audi, Leeds Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Kirklees6.8
Ellis Hill Trading Estate, Leeds Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Kirklees6.9
Bow Beck Bowling, Back Lanerooftop solarrooftop solar0.2approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Bradford6.9
Trafalgar House Police Station - Installation Of Solar PV Systemrooftop solarrooftop solar—under constructionupdated Sep 2023——Sep 2023Bradford7.2
Calder Textiles, Dewsbury Mills Solar Photovoltaic Equipmentrooftop solarrooftop solar—approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Kirklees7.2
Sainsburys, Railway Streetrooftop solarrooftop solar0.4approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Kirklees7.3
New Street Mills, Carlisle Roadrooftop solarrooftop solar—approved, not builtupdated Nov 2025Sep 2025granted Oct 2025Nov 2025Leeds7.5
University of Bradford, Richmond Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2022Sep 2022granted Nov 2022Nov 2022Bradford7.8
Huddersfield Town Sports Academy, Leeds Roadrooftop solarrooftop solar0.1approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Kirklees8.0
Lowfields Business Park, Lowfields Wayrooftop solarrooftop solar0.6approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Calderdale8.0
United Anodisers, Red Doles Lanerooftop solarrooftop solar0.3under constructionupdated Apr 2023Dec 2022—Apr 2023Kirklees8.2
Crawshaw Academy, Robin Lanerooftop solarrooftop solar0.2approved, not built may be out of dateupdated May 2023Mar 2023granted May 2023May 2023Leeds8.3
Pudsey Leisure Centrerooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Sep 2023granted Feb 2024Feb 2024Leeds8.3
Zains Superstore, Legrams Lanebattery storagebattery storage—refusedupdated Apr 2024Feb 2024refused Apr 2024Apr 2024Bradford8.4
Spire Elland Hospitalrooftop solarrooftop solar0.2approved, not builtupdated May 2025Dec 2024granted Apr 2025May 2025Calderdale8.7
John Smiths Stadium, Huddersfield Townrooftop solarrooftop solar0.5approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Kirklees8.9
Duncombe Roadbattery storagebattery storage—application withdrawnupdated Apr 2026Sep 2025—Apr 2026Bradford9.0
The University Of Bradford Stadiumrooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Bradford9.0
Morrisons, Thornton Roadrooftop solarrooftop solar0.9approved, not builtupdated Jan 2022Jan 2022granted Mar 2022Jan 2022Bradford9.2
Clayton Ce Primary Schoolrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Bradford9.3
Eureka, Discovery Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024Calderdale9.3
Spring Valley Millsrooftop solarrooftop solar0.4approved, not builtupdated May 2022Mar 2022granted Apr 2022May 2022Leeds9.3
Sainsburys, Wade Streetrooftop solarrooftop solar0.8approved, not builtApr 2026granted Jun 2026—Calderdale9.3
Cummins Turbo Technology, St Andrews Road Solar PV Canopiessolar farmsolar farm—application submittedupdated May 2026Mar 2026—May 2026Kirklees9.6
Cummins Turbo Technologies, St Andrews Roadrooftop solarrooftop solar0.9approved, not builtupdated Jul 2023Jun 2023granted Jul 2023Jul 2023Kirklees9.6
Cummins Turbo Technologies, St Andrews Roadrooftop solarrooftop solar0.5approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Kirklees9.7
West Specialist Inclusive Learning Centre, Town Streetrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024Leeds9.8
Greenhill Primary School, Gamble Hill Driverooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Leeds9.9

Distance from the average position of the BD19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm421103.4
Rooftop solar381370015.6
Wind turbine200010
Battery storage90701234

MW in pipeline: pending, approved and under-construction capacity.

How Kirklees decides solar, wind and battery applications

ApplicationsKirkleesUK
Decided applications (solar, wind, battery)2610,236
Refused2 (8%)19%
Solar refused0 of 2212%
Onshore wind refused2 of 245%
Battery storage refused0 of 216%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

All projects in Kirklees

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BD19, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.