Aston Martin Lagonda, Banbury Road (5.2 MW rooftop solar)
Aston Martin Lagonda, Banbury Road is a 5.2 MW rooftop solar project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 October 2024, not yet built; the record was last updated on 28 October 2024.
5.2 MWrooftop solar
approved, not builtstatus in REPD
28 October 2024record last updated
Stratford-on-Avoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 16 August 2024 | Application submitted |
| 10 October 2024 | Planning permission granted |
Project details
- Technology
- rooftop solar
- Capacity
- 5.2 MW
- Status (REPD)
- approved, not built
- Record last updated
- 28 October 2024
- Operator or applicant
- Aston Martin Head Office
- Planning authority
- Stratford-on-Avon
- Planning application reference
- 24/02075/PVN
- Address (REPD)
- Aston Martin Lagonda Banbury Road Gaydon
- Council area (by location)
- Stratford-on-Avon
- Time to decision
- 8 weeks
- Name in REPD
- Aston Martin Lagonda, Banbury Road - Solar panels
- REPD reference
- 16945
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Aston Martin Lagonda, Banbury Road 24/01520/PVN | 5.2 | 20 June 2024 | withdrawn 12 August 2024 |
Who decides
| Applications | Stratford-on-Avon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 8 (18%) | 19% |
| Solar refused | 5 of 36 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 2 of 8 | 16% |
| Median time from submission to decision | 18.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Banbury Road, Gaydon | solar farm | 18 | operational | <0.1 |
| Starbold Wind Farm | wind farm | 15 | refused on appeal | 3.2 |
| The Elms | solar farm | 10.4 | operational | 3.4 |
| Moreton Morrell | solar farm | 20 | approved, not built | 3.5 |
| Feldon Vale Solar Farm | solar farm | 49.9 | operational | 3.7 |
| Feldon Vale Solar Farm | solar farm | 49.9 | approved, not built | 3.7 |
| Ashorne Hill Solar Farm | solar farm | 50 | approved, not built | 4.3 |
| Dadglow Farm, Bishops Itchington | battery storage | 20 | refused | 4.7 |
| Deppers Bridge | solar | 9 | refused | 6.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1946, -1.4844).