Energy Projects Near You

Solar, wind and battery projects near Leamington Spa (CV33)

42 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CV33 (Stratford-on-Avon): 21 approved but not yet running, 10 operational. The largest live scheme is Middle Road Farm Solar Farm & Battery Storage (50 MW solar farm, approved on 18 August 2023, not yet built), 0.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42projects within 10 km
0awaiting a decision
21approved, not running
10operational

Projects within 10 km of CV33

Projects of 1 MW and more (23)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Fosse Way Solar Farmsolar farmsolar farm50refusedupdated Jul 2025Oct 2024refused May 2025Jul 2025Warwick0.8
Land On The East Side Of Fosse Waysolar farmsolar farm10operationalupdated Apr 2017Jul 2015granted Nov 2015Apr 2017Warwick0.9
Middle Road Farm Solar Farm & Battery Storagesolar farmsolar farm50approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Stratford-on-Avon0.9
Ashorne Hill Solar Farmsolar farmsolar farm50approved, not built may be out of dateupdated Aug 2022Sep 2021granted Aug 2022Aug 2022Stratford-on-Avon2.3
Tollgate Farmsolar farmsolar farm4.3operationalupdated Aug 2016Aug 2014granted Jan 2015Aug 2016Warwick4.0
Wolseley National Distribution Centrerooftop solarrooftop solar2operationalupdated Apr 2014——Apr 2014Warwick4.2
Brickyard Barnsolar farmsolar farm4.1operationalupdated Nov 2014Nov 2013granted Dec 2013Nov 2014Warwick4.5
Eastfields Farm, Deppers Bridge Solar Farmsolar farmsolar farm34.8under constructionupdated May 2024Jul 2021granted Aug 2021May 2024Stratford-on-Avon4.5
The Elmssolar farmsolar farm10.4operationalupdated Jul 2015Sep 2014granted Nov 2014Jul 2015Stratford-on-Avon4.9
Deppers Bridgesolarsolar9refusedupdated Jun 2014Oct 2013refused Apr 2014Jun 2014Stratford-on-Avon5.2
Solar Farm at Fields Farm (Phase 1)solar farmsolar farm5operationalupdated Sep 2016Mar 2015granted Jun 2015Sep 2016Stratford-on-Avon5.4
Solar Farm at Fields Farm (Phase 2)solar farmsolar farm3.8abandonedupdated Nov 2016Mar 2015granted Jun 2015Nov 2016Stratford-on-Avon5.4
Dadglow Farm, Bishops Itchingtonbattery storagebattery storage20refusedupdated May 2025Oct 2024refused Feb 2025May 2025Stratford-on-Avon5.7
Banbury Road, Gaydonsolar farmsolar farm18operationalupdated Aug 2025Nov 2022granted Mar 2023Aug 2025Stratford-on-Avon6.0
Aston Martin Lagonda, Banbury Roadrooftop solarrooftop solar5.2approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Stratford-on-Avon6.0
Starbold Wind Farmwind farmwind farm15refused on appealupdated Sep 2014Apr 2012refused Feb 2013Sep 2014Stratford-on-Avon6.2
Moreton Morrellsolar farmsolar farm20approved, not builtupdated Feb 2026Sep 2024granted Jul 2025Feb 2026Stratford-on-Avon6.4
Weddington Farmsolar farmsolar farm2.1operationalupdated Nov 2019Sep 2015granted Sep 2016Nov 2019Stratford-on-Avon6.5
Newbold Pacey Solar Farmsolar farmsolar farm28.7operationalupdated Jan 2025Feb 2022granted Aug 2022Jan 2025Stratford-on-Avon6.7
Feldon Vale Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2021Oct 2020granted Aug 2021Feb 2021Stratford-on-Avon7.0
Feldon Vale Solar Farmsolar farmsolar farm49.9operationalupdated Feb 2023Sep 2022—Feb 2023Stratford-on-Avon7.0
Bascote Road Solar Farmsolar farmsolar farm4.6permission expiredupdated Dec 2019Jun 2015granted Sep 2016Dec 2019Stratford-on-Avon7.2
Sherbourne Warwick Solar (Hampton Lodge)solar farmsolar farm20approved, not builtupdated Feb 2026May 2022granted Sep 2023Feb 2026Warwick9.4
Smaller schemes under 1 MW, mostly rooftop solar (19)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Radford Solar Farmbattery storagebattery storage—abandonedupdated Mar 2019Jun 2017—Mar 2019Warwick0.8
Fosse Waybattery storagebattery storage—refusedupdated Jul 2025Oct 2024refused May 2025Jul 2025Warwick0.8
Middle Road Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Stratford-on-Avon0.9
Ashorne Hill Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated May 2025Sep 2021granted Aug 2022May 2025Stratford-on-Avon2.3
Barnwell Poultry Farm, Harbury Lanerooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Warwick2.7
Unit 12, Sydenham Industrial Estaterooftop solarrooftop solar0.3approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022Warwick3.8
Eastfields Farm, Harburybattery storagebattery storage—under constructionupdated May 2024Jul 2021granted Oct 2021May 2024Stratford-on-Avon4.3
Guide Dogs National Breeding Centre, Banbury Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2024Aug 2023granted Sep 2023Jan 2024Warwick4.3
Bishops Bowl Fisherybattery storagebattery storage—approved, not builtupdated Oct 2023Jul 2023granted Oct 2023Oct 2023Stratford-on-Avon4.6
Lower Farmsolar farmsolar farm0.5under constructionupdated Dec 2019Oct 2018granted Oct 2020Dec 2019Stratford-on-Avon4.8
Newbold Comyn Leisure Centre, Newbold Terrace Eastrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Nov 2024granted Nov 2024Jan 2025Warwick5.0
Sainsburys Supermarket, Tachbrook Park Driverooftop solarrooftop solar0.6approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025Warwick5.2
Gaydon Road, Bishops Itchingtonrooftop solarrooftop solar0.2approved, not builtupdated Mar 2022Feb 2022granted Apr 2022Mar 2022Stratford-on-Avon5.6
Jaguar Land Rover Kingsway Batterybattery storagebattery storage—permission expiredupdated May 2020Dec 2015—May 2020Stratford-on-Avon6.2
Leisure Centre, St Nicholas Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Feb 2025granted Apr 2025Jan 2026Warwick7.1
British Film Institute Solar Arrayssolar farmsolar farm0.2approved, not built may be out of dateupdated Jan 2022Oct 2021granted Dec 2021Jan 2022Stratford-on-Avon7.5
Sodick Europe Limited, Agincourt Roadrooftop solarrooftop solar0.2approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Warwick8.2
Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Apr 2026Oct 2025refused Jan 2026Apr 2026Warwick8.3
The Warwickshire Golf and Country Club, Warwick Roadrooftop solarrooftop solar0.1refusedupdated Apr 2024Feb 2024refused Apr 2024Apr 2024Warwick9.0

Distance from the average position of the CV33 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200891225
Rooftop solar1109117.4
Solar100010
Wind farm100010
Battery storage904030

MW in pipeline: pending, approved and under-construction capacity.

How Stratford-on-Avon decides solar, wind and battery applications

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

All projects in Stratford-on-Avon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CV33, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.