Energy Projects Near You

Solar, wind and battery projects near Leamington Spa (CV32)

36 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CV32 (Warwick): 1 is waiting for a planning decision, 23 approved but not yet running, 5 operational. The largest live scheme is Holly Lane Energy Park Solar Farm & Battery Storage (75 MW battery storage, approved on 30 January 2025, not yet built), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36projects within 10 km
1awaiting a decision
23approved, not running
5operational

Projects within 10 km of CV32

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wolseley National Distribution Centrerooftop solarrooftop solar2operationalupdated Apr 2014——Apr 2014Warwick2.7
Brickyard Barnsolar farmsolar farm4.1operationalupdated Nov 2014Nov 2013granted Dec 2013Nov 2014Warwick5.5
Fosse Way Solar Farmsolar farmsolar farm50refusedupdated Jul 2025Oct 2024refused May 2025Jul 2025Warwick5.7
Land On The East Side Of Fosse Waysolar farmsolar farm10operationalupdated Apr 2017Jul 2015granted Nov 2015Apr 2017Warwick6.0
Banner Hill Farm, Banner Hill & Rouncil Lanebattery storagebattery storage49.9refusedupdated Oct 2022Aug 2022refused Sep 2022Oct 2022Warwick6.1
Middle Road Farm Solar Farm & Battery Storagesolar farmsolar farm50approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Stratford-on-Avon6.4
Tollgate Farmsolar farmsolar farm4.3operationalupdated Aug 2016Aug 2014granted Jan 2015Aug 2016Warwick7.1
Leamington Road, Princethorpe - Ash Tree Solar Photovoltaic Arrayssolar farmsolar farm16.8approved, not builtupdated Dec 2025May 2024granted Aug 2025Dec 2025Rugby7.5
Ashorne Hill Solar Farmsolar farmsolar farm50approved, not built may be out of dateupdated Aug 2022Sep 2021granted Aug 2022Aug 2022Stratford-on-Avon7.7
Sherbourne Warwick Solar (Hampton Lodge)solar farmsolar farm20approved, not builtupdated Feb 2026May 2022granted Sep 2023Feb 2026Warwick8.0
Bascote Road Solar Farmsolar farmsolar farm4.6permission expiredupdated Dec 2019Jun 2015granted Sep 2016Dec 2019Stratford-on-Avon9.1
Sherbourne Solar Farmsolar farmsolar farm25approved, not builtupdated Sep 2023Feb 2023granted Aug 2023Sep 2023Stratford-on-Avon9.3
Holly Lane Energy Park Solar Farm & Battery Storagebattery storagebattery storage75approved, not builtupdated Feb 2026Sep 2023granted Jan 2025Feb 2026Solihull9.6
Eastfields Farm, Deppers Bridge Solar Farmsolar farmsolar farm34.8under constructionupdated May 2024Jul 2021granted Aug 2021May 2024Stratford-on-Avon9.9
Newbold Pacey Solar Farmsolar farmsolar farm28.7operationalupdated Jan 2025Feb 2022granted Aug 2022Jan 2025Stratford-on-Avon9.9
Smaller schemes under 1 MW, mostly rooftop solar (21)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Newbold Comyn Leisure Centre, Newbold Terrace Eastrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Nov 2024granted Nov 2024Jan 2025Warwick1.3
Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Apr 2026Oct 2025refused Jan 2026Apr 2026Warwick2.1
Unit 12, Sydenham Industrial Estaterooftop solarrooftop solar0.3approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022Warwick2.5
Sainsburys Supermarket, Tachbrook Park Driverooftop solarrooftop solar0.6approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025Warwick2.5
The Warwickshire Golf and Country Club, Warwick Roadrooftop solarrooftop solar0.1refusedupdated Apr 2024Feb 2024refused Apr 2024Apr 2024Warwick3.6
Leisure Centre, St Nicholas Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Feb 2025granted Apr 2025Jan 2026Warwick3.7
Barnwell Poultry Farm, Harbury Lanerooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Warwick4.7
Fosse Waybattery storagebattery storage—refusedupdated Jul 2025Oct 2024refused May 2025Jul 2025Warwick5.7
Radford Solar Farmbattery storagebattery storage—abandonedupdated Mar 2019Jun 2017—Mar 2019Warwick5.8
Castle Farm Recreation Ground, Fishponds Roadrooftop solarrooftop solar—approved, not builtupdated Apr 2025Feb 2025granted Apr 2025Apr 2025Warwick6.0
Middle Road Farm Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Stratford-on-Avon6.4
Sodick Europe Limited, Agincourt Roadrooftop solarrooftop solar0.2approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Warwick6.5
Guide Dogs National Breeding Centre, Banbury Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2024Aug 2023granted Sep 2023Jan 2024Warwick7.4
Ashorne Hill Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated May 2025Sep 2021granted Aug 2022May 2025Stratford-on-Avon7.7
Canute Haulage Group, Siskin Parkway Eastrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024Warwick8.5
Siskin Parkway East, Middlemarch Business Parkrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Mar 2022Dec 2022granted Feb 2023Mar 2022Warwick8.5
UKBIC, Rowley Roadrooftop solarrooftop solar—application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023Warwick8.7
Lower Farmsolar farmsolar farm0.5under constructionupdated Dec 2019Oct 2018granted Oct 2020Dec 2019Stratford-on-Avon9.1
Sherbourne Solar Farmbattery storagebattery storage—approved, not builtupdated Sep 2023Feb 2023granted Aug 2023Sep 2023Stratford-on-Avon9.3
Ree Automotive Uk, Siskin Driverooftop solarrooftop solar0.6approved, not builtupdated Mar 2025Feb 2025granted Apr 2025Mar 2025Warwick9.4
Eastfields Farm, Harburybattery storagebattery storage—under constructionupdated May 2024Jul 2021granted Oct 2021May 2024Stratford-on-Avon9.5

Distance from the average position of the CV32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm130741197
Rooftop solar14111113
Battery storage9050375

MW in pipeline: pending, approved and under-construction capacity.

How Warwick decides solar, wind and battery applications

ApplicationsWarwickUK
Decided applications (solar, wind, battery)2010,236
Refused8 (40%)19%
Solar refused4 of 1612%
Battery storage refused4 of 416%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Warwick

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CV32, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.