Newbold Pacey Solar Farm (28.7 MW)

Newbold Pacey Solar Farm is a 28.7 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 November 2024; the record was last updated on 28 January 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28.7 MWsolar farm
operationalstatus in REPD
28 January 2025record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
7 February 2022Application submitted
24 August 2022Planning permission granted
1 November 2024Operational

Project details

Technology
solar farm
Capacity
28.7 MW
Status (REPD)
operational
Record last updated
28 January 2025
Operator or applicant
Innova Renewables / ISGRenewables
Planning authority
Stratford-on-Avon
Planning application reference
22/00003/FUL
Site area
18.1 ha
Address (REPD)
N/O B4087 Elms Farm, Newbold Pacey, Warwick
Council area (by location)
Stratford-on-Avon
Time to decision
28 weeks
REPD reference
9631

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Moreton Morrellsolar farm20approved, not built2.7
Ashorne Hill Solar Farmsolar farm50approved, not built4.7
Aston Martin Lagonda, Banbury Roadrooftop solar5.2approved, not built6.0
Banbury Road, Gaydonsolar farm18operational6.0
Sherbourne Solar Farmsolar farm25approved, not built6.3
Sherbourne Warwick Solar (Hampton Lodge)solar farm20approved, not built6.4
Fosse Way Solar Farmsolar farm50refused7.4
Land On The East Side Of Fosse Waysolar farm10operational7.6
Middle Road Farm Solar Farm & Battery Storagesolar farm50approved, not built7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2117, -1.5686).