Sherbourne Warwick Solar (Hampton Lodge) (20 MW)
Sherbourne Warwick Solar (Hampton Lodge) is a 20 MW solar farm project in Warwick, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 September 2023, not yet built; the record was last updated on 27 February 2026.
20 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
Warwickcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 30 May 2022 | Application submitted |
| 26 August 2022 | Refused by the planning authority |
| 23 February 2023 | Appeal lodged |
| 25 September 2023 | Planning permission granted |
| 25 September 2023 | Appeal allowed |
| 25 September 2026 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 20 MW
- Status (REPD)
- approved, not built
- Record last updated
- 27 February 2026
- Operator or applicant
- Pelagic Energy Development
- Planning authority
- Warwick
- Planning application reference
- W/22/0548
- Appeal reference
- APP/T3725/W/23/3317247
- Site area
- 29.8 ha
- Address (REPD)
- W/O A46 Sherbourne.
- Council area (by location)
- Warwick
- Time to decision
- 69 weeks
- Contracts for Difference
- AR7a
- REPD reference
- 11447
Who decides
| Applications | Warwick | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 20 | 10,236 |
| Refused | 8 (40%) | 19% |
| Solar refused | 4 of 16 | 12% |
| Battery storage refused | 4 of 4 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Sherbourne Solar Farm | solar farm | 25 | approved, not built | 1.3 |
| Park Farm (Claverdon) | solar farm | 7.5 | refused on appeal | 5.1 |
| Newbold Pacey Solar Farm | solar farm | 28.7 | operational | 6.4 |
| Banner Hill Farm, Banner Hill & Rouncil Lane | battery storage | 49.9 | refused | 7.9 |
| Ashorne Hill Solar Farm | solar farm | 50 | approved, not built | 8.7 |
| Moreton Morrell | solar farm | 20 | approved, not built | 9.1 |
| Fosse Way Solar Farm | solar farm | 50 | refused | 9.6 |
| Land On The East Side Of Fosse Way | solar farm | 10 | operational | 10.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2571, -1.6275).