Energy Projects Near You

Sherbourne Warwick Solar (Hampton Lodge) (20 MW)

Sherbourne Warwick Solar (Hampton Lodge) is a 20 MW solar farm project in Warwick, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 September 2023, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
Warwickcouncil area

Planning timeline

DateStage
30 May 2022Application submitted
26 August 2022Refused by the planning authority
23 February 2023Appeal lodged
25 September 2023Planning permission granted
25 September 2023Appeal allowed
25 September 2026Permission expired

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Pelagic Energy Development
Planning authority
Warwick
Planning application reference
W/22/0548
Appeal reference
APP/T3725/W/23/3317247
Site area
29.8 ha
Address (REPD)
W/O A46 Sherbourne.
Council area (by location)
Warwick
Time to decision
69 weeks
Contracts for Difference
AR7a
REPD reference
11447

Who decides

ApplicationsWarwickUK
Decided applications (solar, wind, battery)2010,236
Refused8 (40%)19%
Solar refused4 of 1612%
Battery storage refused4 of 416%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sherbourne Solar Farmsolar farm25approved, not built1.3
Park Farm (Claverdon)solar farm7.5refused on appeal5.1
Newbold Pacey Solar Farmsolar farm28.7operational6.4
Banner Hill Farm, Banner Hill & Rouncil Lanebattery storage49.9refused7.9
Ashorne Hill Solar Farmsolar farm50approved, not built8.7
Moreton Morrellsolar farm20approved, not built9.1
Fosse Way Solar Farmsolar farm50refused9.6
Land On The East Side Of Fosse Waysolar farm10operational10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2571, -1.6275).