Energy Projects Near You

Ashorne Hill Solar Farm (50 MW)

Ashorne Hill Solar Farm is a 50 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 August 2022, not yet built; the record was last updated on 12 August 2022. REPD records the planning permission as expiring on 3 August 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
approved, not builtmay be out of datestatus in REPD
12 August 2022record last updated
Stratford-on-Avoncouncil area

REPD records the planning permission as expiring on 3 August 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
23 September 2021Application submitted
3 August 2022Planning permission granted
3 August 2025Permission expired

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
12 August 2022
Operator or applicant
JBM Solar Projects Limited
Planning authority
Stratford-on-Avon
Planning application reference
W/21/1801
Site area
100.1 ha
Address (REPD)
Ashorne Hill, Bishops Tachbrook, Leamington Spa
Council area (by location)
Stratford-on-Avon
Time to decision
45 weeks
Contracts for Difference
AR5
Name in REPD
Ashorne Hill - Solar Farm
REPD reference
9441

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fosse Way Solar Farmsolar farm50refused3.1
Middle Road Farm Solar Farm & Battery Storagesolar farm50approved, not built3.1
Land On The East Side Of Fosse Waysolar farm10operational3.1
Moreton Morrellsolar farm20approved, not built4.1
Banbury Road, Gaydonsolar farm18operational4.3
Aston Martin Lagonda, Banbury Roadrooftop solar5.2approved, not built4.3
The Elmssolar farm10.4operational4.6
Newbold Pacey Solar Farmsolar farm28.7operational4.7
Eastfields Farm, Deppers Bridge Solar Farmsolar farm34.8under construction5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2308, -1.5074).