Ashorne Hill Solar Farm (50 MW)
Ashorne Hill Solar Farm is a 50 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 August 2022, not yet built; the record was last updated on 12 August 2022. REPD records the planning permission as expiring on 3 August 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.
REPD records the planning permission as expiring on 3 August 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.
Planning timeline
| Date | Stage |
|---|---|
| 23 September 2021 | Application submitted |
| 3 August 2022 | Planning permission granted |
| 3 August 2025 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 50 MW
- Status (REPD)
- approved, not built
- Record last updated
- 12 August 2022
- Operator or applicant
- JBM Solar Projects Limited
- Planning authority
- Stratford-on-Avon
- Planning application reference
- W/21/1801
- Site area
- 100.1 ha
- Address (REPD)
- Ashorne Hill, Bishops Tachbrook, Leamington Spa
- Council area (by location)
- Stratford-on-Avon
- Time to decision
- 45 weeks
- Contracts for Difference
- AR5
- Name in REPD
- Ashorne Hill - Solar Farm
- REPD reference
- 9441
The scheme also includes battery storage, recorded separately in REPD (approved, not built).
Who decides
| Applications | Stratford-on-Avon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 8 (18%) | 19% |
| Solar refused | 5 of 36 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 2 of 8 | 16% |
| Median time from submission to decision | 18.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Fosse Way Solar Farm | solar farm | 50 | refused | 3.1 |
| Middle Road Farm Solar Farm & Battery Storage | solar farm | 50 | approved, not built | 3.1 |
| Land On The East Side Of Fosse Way | solar farm | 10 | operational | 3.1 |
| Moreton Morrell | solar farm | 20 | approved, not built | 4.1 |
| Banbury Road, Gaydon | solar farm | 18 | operational | 4.3 |
| Aston Martin Lagonda, Banbury Road | rooftop solar | 5.2 | approved, not built | 4.3 |
| The Elms | solar farm | 10.4 | operational | 4.6 |
| Newbold Pacey Solar Farm | solar farm | 28.7 | operational | 4.7 |
| Eastfields Farm, Deppers Bridge Solar Farm | solar farm | 34.8 | under construction | 5.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2308, -1.5074).