Energy Projects Near You

Eastfields Farm, Deppers Bridge Solar Farm (34.8 MW)

Eastfields Farm, Deppers Bridge Solar Farm is a 34.8 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 November 2023; the record was last updated on 20 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34.8 MWsolar farm
under constructionstatus in REPD
20 May 2024record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
29 July 2021Application submitted
26 August 2021Planning permission granted
1 November 2023Construction started

Project details

Technology
solar farm
Capacity
34.8 MW
Status (REPD)
under construction
Record last updated
20 May 2024
Operator or applicant
Vantage RE
Planning authority
Stratford-on-Avon
Planning application reference
21/02448/FUL
Site area
67.0 ha
Address (REPD)
Eastfields Farm Deppers Bridge Southam
Council area (by location)
Stratford-on-Avon
Time to decision
4 weeks
Contracts for Difference
AR4
Name in REPD
Eastfields Farm, Deppers Bridge - Solar Farm
REPD reference
9173

Recorded together with Eastfields Farm, Harbury (battery storage, under construction).

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Deppers Bridgesolar9refused0.8
Solar Farm at Fields Farm (Phase 1)solar farm5operational1.4
Dadglow Farm, Bishops Itchingtonbattery storage20refused2.2
The Elmssolar farm10.4operational2.8
Middle Road Farm Solar Farm & Battery Storagesolar farm50approved, not built3.8
Starbold Wind Farmwind farm15refused on appeal3.9
Land On The East Side Of Fosse Waysolar farm10operational4.2
Feldon Vale Solar Farmsolar farm49.9approved, not built4.4
Feldon Vale Solar Farmsolar farm49.9operational4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2368, -1.4262).