Eastfields Farm, Deppers Bridge Solar Farm (34.8 MW)
Eastfields Farm, Deppers Bridge Solar Farm is a 34.8 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 November 2023; the record was last updated on 20 May 2024.
34.8 MWsolar farm
under constructionstatus in REPD
20 May 2024record last updated
Stratford-on-Avoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 July 2021 | Application submitted |
| 26 August 2021 | Planning permission granted |
| 1 November 2023 | Construction started |
Project details
- Technology
- solar farm
- Capacity
- 34.8 MW
- Status (REPD)
- under construction
- Record last updated
- 20 May 2024
- Operator or applicant
- Vantage RE
- Planning authority
- Stratford-on-Avon
- Planning application reference
- 21/02448/FUL
- Site area
- 67.0 ha
- Address (REPD)
- Eastfields Farm Deppers Bridge Southam
- Council area (by location)
- Stratford-on-Avon
- Time to decision
- 4 weeks
- Contracts for Difference
- AR4
- Name in REPD
- Eastfields Farm, Deppers Bridge - Solar Farm
- REPD reference
- 9173
Recorded together with Eastfields Farm, Harbury (battery storage, under construction).
Who decides
| Applications | Stratford-on-Avon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 8 (18%) | 19% |
| Solar refused | 5 of 36 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 2 of 8 | 16% |
| Median time from submission to decision | 18.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Deppers Bridge | solar | 9 | refused | 0.8 |
| Solar Farm at Fields Farm (Phase 1) | solar farm | 5 | operational | 1.4 |
| Dadglow Farm, Bishops Itchington | battery storage | 20 | refused | 2.2 |
| The Elms | solar farm | 10.4 | operational | 2.8 |
| Middle Road Farm Solar Farm & Battery Storage | solar farm | 50 | approved, not built | 3.8 |
| Starbold Wind Farm | wind farm | 15 | refused on appeal | 3.9 |
| Land On The East Side Of Fosse Way | solar farm | 10 | operational | 4.2 |
| Feldon Vale Solar Farm | solar farm | 49.9 | approved, not built | 4.4 |
| Feldon Vale Solar Farm | solar farm | 49.9 | operational | 4.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2368, -1.4262).