Starbold Wind Farm (15 MW)

Starbold Wind Farm is a 15 MW wind farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 1 October 2014; the record was last updated on 16 September 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
refused on appealstatus in REPD
16 September 2014record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
4 April 2012Application submitted
13 February 2013Refused by the planning authority
3 April 2014Appeal lodged
1 October 2014Appeal refused

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
refused on appeal
Record last updated
16 September 2014
Operator or applicant
Broadview Energy
Planning authority
Stratford-on-Avon
Planning application reference
12/00330/FUL
Appeal reference
APP/J3720/A/13/2193579/NWF
Turbines
5
Address (REPD)
Knightcote, Stratford on Avon
Council area (by location)
Stratford-on-Avon
Time to decision
45 weeks
REPD reference
4530

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Feldon Vale Solar Farmsolar farm49.9operational0.8
Feldon Vale Solar Farmsolar farm49.9approved, not built0.8
The Elmssolar farm10.4operational1.4
Dadglow Farm, Bishops Itchingtonbattery storage20refused1.8
Aston Martin Lagonda, Banbury Roadrooftop solar5.2approved, not built3.2
Banbury Road, Gaydonsolar farm18operational3.2
Deppers Bridgesolar9refused3.4
Eastfields Farm, Deppers Bridge Solar Farmsolar farm34.8under construction3.9
Solar Farm at Fields Farm (Phase 1)solar farm5operational5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2025, -1.4387).