Deppers Bridge (9 MW solar)
Deppers Bridge is a 9 MW solar project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 9 April 2014; the record was last updated on 20 June 2014.
9 MWsolar
refusedstatus in REPD
20 June 2014record last updated
Stratford-on-Avoncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 18 October 2013 | Application submitted |
| 9 April 2014 | Refused by the planning authority |
Project details
- Technology
- solar
- Capacity
- 9 MW
- Status (REPD)
- refused
- Record last updated
- 20 June 2014
- Operator or applicant
- Solar Power South
- Planning authority
- Stratford-on-Avon
- Planning application reference
- 13/02689/FUL
- Address (REPD)
- Land At Deppers Bridge Southam
- Council area (by location)
- Stratford-on-Avon
- Time to decision
- 25 weeks
- REPD reference
- 1770
Who decides
| Applications | Stratford-on-Avon | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 45 | 10,236 |
| Refused | 8 (18%) | 19% |
| Solar refused | 5 of 36 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 2 of 8 | 16% |
| Median time from submission to decision | 18.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 4 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Eastfields Farm, Deppers Bridge Solar Farm | solar farm | 34.8 | under construction | 0.8 |
| Dadglow Farm, Bishops Itchington | battery storage | 20 | refused | 1.6 |
| Solar Farm at Fields Farm (Phase 1) | solar farm | 5 | operational | 1.7 |
| The Elms | solar farm | 10.4 | operational | 2.6 |
| Starbold Wind Farm | wind farm | 15 | refused on appeal | 3.4 |
| Feldon Vale Solar Farm | solar farm | 49.9 | operational | 3.8 |
| Feldon Vale Solar Farm | solar farm | 49.9 | approved, not built | 3.8 |
| Middle Road Farm Solar Farm & Battery Storage | solar farm | 50 | approved, not built | 4.5 |
| Land On The East Side Of Fosse Way | solar farm | 10 | operational | 4.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.231, -1.4187).