Energy Projects Near You

Deppers Bridge (9 MW solar)

Deppers Bridge is a 9 MW solar project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 9 April 2014; the record was last updated on 20 June 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWsolar
refusedstatus in REPD
20 June 2014record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
18 October 2013Application submitted
9 April 2014Refused by the planning authority

Project details

Technology
solar
Capacity
9 MW
Status (REPD)
refused
Record last updated
20 June 2014
Operator or applicant
Solar Power South
Planning authority
Stratford-on-Avon
Planning application reference
13/02689/FUL
Address (REPD)
Land At Deppers Bridge Southam
Council area (by location)
Stratford-on-Avon
Time to decision
25 weeks
REPD reference
1770

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Eastfields Farm, Deppers Bridge Solar Farmsolar farm34.8under construction0.8
Dadglow Farm, Bishops Itchingtonbattery storage20refused1.6
Solar Farm at Fields Farm (Phase 1)solar farm5operational1.7
The Elmssolar farm10.4operational2.6
Starbold Wind Farmwind farm15refused on appeal3.4
Feldon Vale Solar Farmsolar farm49.9operational3.8
Feldon Vale Solar Farmsolar farm49.9approved, not built3.8
Middle Road Farm Solar Farm & Battery Storagesolar farm50approved, not built4.5
Land On The East Side Of Fosse Waysolar farm10operational4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.231, -1.4187).