Solar Farm at Fields Farm (Phase 1) (5 MW)

Solar Farm at Fields Farm (Phase 1) is a 5 MW solar farm project in Stratford-on-Avon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2016; the record was last updated on 20 September 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
20 September 2016record last updated
Stratford-on-Avoncouncil area

Planning timeline

DateStage
16 March 2015Application submitted
29 June 2015Planning permission granted
4 January 2016Construction started
23 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
20 September 2016
Operator or applicant
Foresight Group (TGC Renewables)
Planning authority
Stratford-on-Avon
Planning application reference
15/00767/FUL
Site area
16.2 ha
Address (REPD)
Land at Fields Farm, Southam
Council area (by location)
Stratford-on-Avon
Time to decision
15 weeks
REPD reference
5244

Who decides

ApplicationsStratford-on-AvonUK
Decided applications (solar, wind, battery)4510,236
Refused8 (18%)19%
Solar refused5 of 3612%
Onshore wind refused1 of 145%
Battery storage refused2 of 816%
Median time from submission to decision18.0 weeks17.0 weeks
Appeals lodged / allowed6 / 4—

Other large projects within 10 km

ProjectTypeMWStatuskm
Eastfields Farm, Deppers Bridge Solar Farmsolar farm34.8under construction1.4
Deppers Bridgesolar9refused1.7
Dadglow Farm, Bishops Itchingtonbattery storage20refused3.3
The Elmssolar farm10.4operational4.2
Middle Road Farm Solar Farm & Battery Storagesolar farm50approved, not built4.6
Land On The East Side Of Fosse Waysolar farm10operational4.9
Starbold Wind Farmwind farm15refused on appeal5.1
Fosse Way Solar Farmsolar farm50refused5.3
Feldon Vale Solar Farmsolar farm49.9operational5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2449, -1.4102).