Fosse Way Solar Farm (50 MW)

Fosse Way Solar Farm is a 50 MW solar farm project in Warwick, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 22 May 2025; the record was last updated on 15 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
refusedstatus in REPD
15 July 2025record last updated
Warwickcouncil area

Planning timeline

DateStage
15 October 2024Application submitted
22 May 2025Refused by the planning authority

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
refused
Record last updated
15 July 2025
Operator or applicant
Staffordshire Solar 1 Limited
Planning authority
Warwick
Planning application reference
W/24/1404
Site area
86.0 ha
Address (REPD)
W/O Fosse Way, Se/O Radford Semele, Leamington Spa
Council area (by location)
Warwick
Time to decision
31 weeks
Name in REPD
Fosse Way - Solar Farm
REPD reference
17429

Who decides

ApplicationsWarwickUK
Decided applications (solar, wind, battery)2010,236
Refused8 (40%)19%
Solar refused4 of 1612%
Battery storage refused4 of 416%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land On The East Side Of Fosse Waysolar farm10operational0.4
Middle Road Farm Solar Farm & Battery Storagesolar farm50approved, not built0.8
Ashorne Hill Solar Farmsolar farm50approved, not built3.1
Eastfields Farm, Deppers Bridge Solar Farmsolar farm34.8under construction4.6
Solar Farm at Fields Farm (Phase 1)solar farm5operational5.3
Deppers Bridgesolar9refused5.3
The Elmssolar farm10.4operational5.3
Dadglow Farm, Bishops Itchingtonbattery storage20refused6.0
Starbold Wind Farmwind farm15refused on appeal6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.255, -1.4861).