East Chickerell Court Farm (400 MW battery storage)

East Chickerell Court Farm is a 400 MW battery storage project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 January 2025, not yet built; the record was last updated on 11 February 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
11 February 2025record last updated
Dorsetcouncil area

Planning timeline

DateStage
14 August 2023Application submitted
27 January 2025Planning permission granted
27 January 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
11 February 2025
Operator or applicant
Statera Energy
Planning authority
Dorset
Planning application reference
P/FUL/2023/04657
Address (REPD)
East Chickerell Court Farm, Chickerell, Weymouth
Council area (by location)
Dorset
Time to decision
76 weeks
Name in REPD
East Chickerell Court Farm - Battery Energy Storage System
REPD reference
12651

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Newlands Farmsolar farm5operational0.3
Coldharbour, Chickerellbattery storage60refused0.4
Eweleaze Spinneybattery storage49.9approved, not built0.6
Buckland Battery Storagebattery storage150refused1.8
Nottington Lane Solar Farmsolar farm5operational2.0
Corton Farmsolar farm10refused4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6286, -2.4903).