Eweleaze Spinney (49.9 MW battery storage)

Eweleaze Spinney is a 49.9 MW battery storage project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 April 2025, not yet built; the record was last updated on 28 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
28 April 2025record last updated
Dorsetcouncil area

Planning timeline

DateStage
4 September 2024Application submitted
4 April 2025Planning permission granted
4 April 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
28 April 2025
Operator or applicant
Weymouth Battery Limited
Planning authority
Dorset
Planning application reference
P/FUL/2024/04447
Address (REPD)
N/O Eweleaze Spinney, Weymouth
Council area (by location)
Dorset
Time to decision
30 weeks
Name in REPD
Eweleaze Spinney - Battery Energy Storage Facility
REPD reference
17121

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Chickerell Court Farmbattery storage400approved, not built0.6
Land at Newlands Farmsolar farm5operational0.7
Coldharbour, Chickerellbattery storage60refused0.9
Buckland Battery Storagebattery storage150refused2.4
Nottington Lane Solar Farmsolar farm5operational2.6
Corton Farmsolar farm10refused5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6235, -2.4879).