Land at Newlands Farm (5 MW solar farm)

Land at Newlands Farm is a 5 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2016; the record was last updated on 14 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
14 April 2016record last updated
Dorsetcouncil area

Planning timeline

DateStage
13 October 2014Application submitted
17 December 2014Planning permission granted
8 June 2015Construction started
15 February 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
14 April 2016
Operator or applicant
British Solar Renewables
Planning authority
Dorset
Planning application reference
WD/D/14/002675
Site area
7.4 ha
Address (REPD)
Newlands Farm, Chickerell, West Dorset
Council area (by location)
Dorset
Time to decision
9 weeks
REPD reference
4703

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
East Chickerell Court Farmbattery storage400approved, not built0.3
Coldharbour, Chickerellbattery storage60refused0.4
Eweleaze Spinneybattery storage49.9approved, not built0.7
Buckland Battery Storagebattery storage150refused1.8
Nottington Lane Solar Farmsolar farm5operational1.9
Corton Farmsolar farm10refused4.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6278, -2.4948).