Nottington Lane Solar Farm (5 MW)

Nottington Lane Solar Farm is a 5 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2013; the record was last updated on 4 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 June 2013record last updated
Dorsetcouncil area

Planning timeline

DateStage
31 May 2012Application submitted
20 September 2012Planning permission granted
18 January 2013Construction started
30 March 2013Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 June 2013
Operator or applicant
PS Renewables
Planning authority
Dorset
Planning application reference
1/D/12/000858
Site area
18.7 ha
Address (REPD)
North Farm, Nottington Lane, Buckland Ripers, Weymouth
Council area (by location)
Dorset
Time to decision
16 weeks
Name in REPD
NOTTINGTON LANE SOLAR FARM
REPD reference
1090

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Buckland Battery Storagebattery storage150refused0.5
Coldharbour, Chickerellbattery storage60refused1.6
Land at Newlands Farmsolar farm5operational1.9
East Chickerell Court Farmbattery storage400approved, not built2.0
Eweleaze Spinneybattery storage49.9approved, not built2.6
Corton Farmsolar farm10refused2.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.6433, -2.5063).