Energy Projects Near You

Ferry Farm (11 MW solar farm)

Ferry Farm is an 11 MW solar farm project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 5 November 2021, not yet built; the record was last updated on 27 January 2025. REPD records the planning permission as expiring on 5 November 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWsolar farm
approved, not builtmay be out of datestatus in REPD
27 January 2025record last updated
Chichestercouncil area

REPD records the planning permission as expiring on 5 November 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
17 June 2021Application submitted
5 November 2021Planning permission granted
5 November 2024Permission expired

Project details

Technology
solar farm
Capacity
11 MW
Status (REPD)
approved, not built
Record last updated
27 January 2025
Operator or applicant
BNRG & Lanlink Estates Limited
Planning authority
Chichester
Planning application reference
21/01816/FULEIA
Site area
28.0 ha
Address (REPD)
Ferry Farm 3 North Chichester Road Selsey
Council area (by location)
Chichester
Time to decision
20 weeks
Contracts for Difference
AR4
Name in REPD
Ferry Farm - Solar array
REPD reference
8498

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Ferry Farmsolar farm10operational3.1
Bakers Farm (solar)solar farm12operational3.8
Mundham, Runcton Lane Solar Farmsolar farm30approved, not built9.0
Park Farmsolar farm5operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.73, -0.7881).