Land At Ferry Farm (10 MW solar farm)

Land At Ferry Farm is a 10 MW solar farm project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2015; the record was last updated on 16 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
16 February 2017record last updated
Chichestercouncil area

Planning timeline

DateStage
10 December 2014Application submitted
7 April 2015Planning permission granted
1 November 2015Construction started
15 December 2015Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
16 February 2017
Operator or applicant
BNRG (sold to another developer)
Planning authority
Chichester
Planning application reference
14/03944/FULEIA
Address (REPD)
Ferry Farm, Chichester Road, Selsey, Chichester, West Sussex
Council area (by location)
Chichester
Time to decision
17 weeks
REPD reference
4931

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bakers Farm (solar)solar farm12operational1.0
Ferry Farmsolar farm11approved, not built3.1
Mundham, Runcton Lane Solar Farmsolar farm30approved, not built6.1
Park Farmsolar farm5operational7.2
Merston Solar Parksolar farm10operational7.7
Manor Farm - Shripneysolar farm5operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.7577, -0.7845).