Energy Projects Near You

Mundham, Runcton Lane Solar Farm (30 MW)

Mundham, Runcton Lane Solar Farm is a 30 MW solar farm project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 March 2026, not yet built; the record was last updated on 27 April 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
27 April 2026record last updated
Chichestercouncil area

Planning timeline

DateStage
21 August 2024Application submitted
12 May 2025Refused by the planning authority
24 February 2026Appeal lodged
11 March 2026Planning permission granted
11 March 2026Appeal allowed
11 March 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
27 April 2026
Operator or applicant
BNRG Renewables Limited
Planning authority
Chichester
Planning application reference
24/01859/FUL
Appeal reference
APP/L3815/W/25/3370586
Site area
49.0 ha
Address (REPD)
S/O Mundham, Runcton Lane, Runcton, Chichester
Council area (by location)
Chichester
Time to decision
81 weeks
Name in REPD
Mundham, Runcton Lane - Solar Farm
REPD reference
17029

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Park Farmsolar farm5operational1.5
Merston Solar Parksolar farm10operational1.6
Manor Farm - Shripneysolar farm5operational4.1
Decoy Farm House Solar Modulessolar farm6operational4.3
Oving Solar Farmsolar farm5operational4.3
Former Westhampnett Landfillsolar farm7.5operational4.8
Land at Tangmere Airfieldsolar farm5operational5.5
Bakers Farm (solar)solar farm12operational5.9
Strettington Solar Farmsolar farm5operational5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8044, -0.7384).