Merston Solar Park (10 MW)

Merston Solar Park is a 10 MW solar farm project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 June 2016; the record was last updated on 27 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
27 June 2016record last updated
Chichestercouncil area

Planning timeline

DateStage
3 October 2014Application submitted
19 March 2015Planning permission granted
1 December 2015Construction started
28 June 2016Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
27 June 2016
Operator or applicant
Primrose Solar / Mongoose Energy
Planning authority
Chichester
Planning application reference
14/02814/FUL
Address (REPD)
Land at Pagham Road, Merston, Chichester
Council area (by location)
Chichester
Time to decision
24 weeks
REPD reference
4713

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Mundham, Runcton Lane Solar Farmsolar farm30approved, not built1.6
Park Farmsolar farm5operational1.7
Oving Solar Farmsolar farm5operational2.8
Decoy Farm House Solar Modulessolar farm6operational3.0
Former Westhampnett Landfillsolar farm7.5operational3.4
Manor Farm - Shripneysolar farm5operational3.5
Land at Tangmere Airfieldsolar farm5operational3.9
Strettington Solar Farmsolar farm5operational4.3
Boxgrove Common, Tinwood Lanebattery storage70approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8181, -0.7317).