Boxgrove Common, Tinwood Lane (70 MW battery storage)

Boxgrove Common, Tinwood Lane is a 70 MW battery storage project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 July 2025, not yet built; the record was last updated on 26 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

70 MWbattery storage
approved, not builtstatus in REPD
26 August 2025record last updated
Chichestercouncil area

Planning timeline

DateStage
25 September 2024Application submitted
23 July 2025Planning permission granted
23 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
70 MW
Status (REPD)
approved, not built
Record last updated
26 August 2025
Operator or applicant
Net Zero Fifteen Limited
Planning authority
Chichester
Planning application reference
24/02040/FUL
Address (REPD)
Boxgrove Common Tinwood Lane Eartham
Council area (by location)
Chichester
Time to decision
43 weeks
Name in REPD
Boxgrove Common, Tinwood Lane - Battery Energy Storage System
REPD reference
17294

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Tangmere Airfieldsolar farm5operational1.9
Oving Solar Farmsolar farm5operational3.1
Strettington Solar Farmsolar farm5operational3.1
Decoy Farm House Solar Modulessolar farm6operational3.7
Former Westhampnett Landfillsolar farm7.5operational4.3
Manor Farm - Shripneysolar farm5operational5.3
Merston Solar Parksolar farm10operational5.8
Bilsham Farmsolar farm14.5operational6.5
Binsted Farmsolar farm5operational6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8622, -0.6868).