Binsted Farm (5 MW solar farm)

Binsted Farm is a 5 MW solar farm project in Arun, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 31 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
31 August 2016record last updated
Aruncouncil area

Planning timeline

DateStage
6 July 2015Application submitted
28 September 2015Planning permission granted
31 January 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
31 August 2016
Operator or applicant
Lightsource BP
Planning authority
Arun
Planning application reference
WA/34/15/PL
Site area
9.9 ha
Address (REPD)
Land East of Yapton Lane, Walberton
Council area (by location)
Arun
Time to decision
12 weeks
REPD reference
6205

Who decides

ApplicationsArunUK
Decided applications (solar, wind, battery)1110,236
Refused0 (0%)19%
Solar refused0 of 1112%
Median time from submission to decision13.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bilsham Farmsolar farm14.5operational3.0
Manor Farm - Shripneysolar farm5operational5.8
Decoy Farm House Solar Modulessolar farm6operational6.1
Boxgrove Common, Tinwood Lanebattery storage70approved, not built6.5
Land at Tangmere Airfieldsolar farm5operational6.9
Oving Solar Farmsolar farm5operational7.0
Park Farmsolar farm5operational8.4
Merston Solar Parksolar farm10operational9.0
Strettington Solar Farmsolar farm5operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8338, -0.6061).